| 24-Mar-2025 |
Sh.
Sumeet, Engineering Officer and Sh. Ashish, Chartered Accountant briefed about
the facts of the project.
Sh.
Praveen Soni (AR) and Sh. Kamal Soni (AR) are present on behalf of the promoter
and states that after completion of the building in all respect, application
for grant of OC has been made to DTCP on 07.03.2025. The license has been
expired recently only on 06.03.2025 and renewal of the same is also applied.
The approval of license renewal is expected within two weeks as the outstanding
amount of EDC and license renewal fees has been deposited with DTCP. Renewed license
will be submitted within two weeks along with other pending deficiencies.
In
view of the above, the extension of registration of project for one year under
section 6 of the Act, 2016 is approved. The certificate shall be issued after
compliance of the above deficiencies mentioned in remarks at s. no. 32. |
EXTENSION APPROVED |
View Order |
| 24-Feb-2025 |
The matter is adjourned and to come up on 24.03.2025. |
ADJOURNMENT |
View Order |
| 05-Feb-2025 |
The matter is adjourned and to come up on 24.02.2025. |
ADJOURNMENT |
View Order |
| 03-Feb-2025 |
The matter is adjourned and to come up on 05.02.2025 at 03:00 PM. |
ADJOURNMENT |
--- |
| 13-Jan-2025 |
Sh.
Sumeet, Engineering Officer and Sh. Ashish, Chartered Accountant briefed about
the facts of the project.
Sh.
Praveen Soni (AR) and Sh. Kamal Kant Soni (AR) are present on behalf of the
promoter and states that after completion of the construction work, the OC has
been applied and expected within 2-3 weeks.
Further,
the AR seeks two weeks’ time to rectify the remaining deficiencies in the
application.
The
matter to come up on 03.02.2025. |
ADJOURNMENT |
View Order |
| 09-Dec-2024 |
The matter is adjourned and to come up on 13.01.2025 |
ADJOURNMENT |
View Order |
| 18-Nov-2024 |
Sh.
Sumeet, Engineering Officer and Sh. Ashish, Chartered Accountant briefed about
the facts of the project.
Sh.
Praveen Soni and Sh. Kamal Soni (AR) are present on behalf of the promoter.
The
AR of the promoter request for two weeks’ time for submission of revalidated
building plans, approved service plan estimates along with other deficit
documents. The same is allowed.
The
matter to come up on 09.12.2024. |
ADJOURNMENT |
View Order |
| 21-Oct-2024 |
The matter is adjourned and to come up on 18.11.2024. |
ADJOURNMENT |
View Order |
| 16-Sep-2024 |
The matter is adjourned and to come up on 21.10.2024. |
ADJOURNMENT |
View Order |
| 12-Aug-2024 |
The matter is adjourned and to come up on 16.09.2024. |
ADJOURNMENT |
View Order |
| 22-Jul-2024 |
The matter is adjourned and to come up on 12.08.2024. |
EXAMINATION BY AUTHORITY |
View Order |