07-Oct-2024 |
Sh. Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered
Accountant briefed about the facts of the case.
Sh. Rohit Kishore (CEO), Sh. Sachin Sharma (Legal Head) and Sh. Vaibhav
Lalit (AR) are present on behalf of the promoter and states that regarding the
complaint filed by M/s Karma Lakeland, a public disclaimer notice regarding
issuance of any advertisement has been published and a police complaint against
the concerned broker has also been lodged. Further, the affidavit through its
director for not making any sale/booking in respect of the units falling under ROW
of 66 KV HT line till its shifting by HSIIDC alongwith the original bank
undertaking will be submitted in the Authority today.
The services to the site are to be provided by HSIIDC as a site forms
part of the township project and all external services are to be provided and
managed by HSIIDC. The promoter shall submit a DD/BG of Rs. 25 lakhs as a
security amount in lieu of submission of Fire Scheme approval within 4 months.
The promoter shall submit the mining permission before start of construction.
Sh. Sandeep Trehan (AR) is present on behalf of the complainants and states
that M/s Karma Lakeland has now no further issue regarding the complaint dated
28.08.24 as a public notice as well as
undertaking has been submitted and necessary legal action is being taken
against the broker who issued advertisement for sale without any authorization.
As proposed, the grant of registration is approved subject to submission
of BG/DD of Rs 25 lakhs alongwith rectification of the above mentioned
deficiencies. The Registration certificate shall be issued after the submission
of above along with necessary corrections in online form A-H and DPI. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
30-Sep-2024 |
The
matter to come up on 07.10.2024. |
ADJOURNMENT |
View Order |
16-Sep-2024 |
Sh.
Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered Accountant
briefed about the facts of the case.
Sh.
Vaibhav Lalit (Legal Manager) is present on behalf of the promoter and states
that two undertakings have been submitted today in the registry and NOC of the
financial institution i.e. HDFC Capital (Vistara) regarding creation of 3rd
party rights in respect of the units. The AR further states that the
clarification along with the details of the specific units which are affected
by two HT lines of 66 KV which are to be shifted by HSIIDC and an undertaking
will also be submitted that the promoter shall not advertise, market or sell
the units in the towers under the HT lines. Further, regarding the provisioning
of services, HSIIDC vide letter dated 25.04.2024 has intimated that water and
sewerage connection etc. will be supplied after completion of infrastructure
services expected up to 30.04.2026. The promoter also to clarify the
provisioning of these services till the same are provided by HSIIDC as no firm
dates have been committed by HSIIDC.
The
matter to come up on 30.09.2024. |
ADJOURNMENT |
View Order |
02-Sep-2024 |
The matter is adjourned and to come up on 16.09.2024. |
EXAMINATION BY AUTHORITY |
View Order |