Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
Eldeco Fairway Reserve Sector-80, Manesar, Gurugram GURUGRAM Manesar ELDECO INFRASTRUCTURE AND PROPERTIES LIMITED
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/880/612/2024/107 DATED 23.10.2024 RERA-GRG-1680-2024 09-Aug-2024 22-Jul-2024 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 30-Aug-2024 BY HAND First Deficiency Notice
First hearing View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/880/612/2024/107 DATED 23.10.2024 14-Nov-2024 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
07-Oct-2024 Sh. Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Rohit Kishore (CEO), Sh. Sachin Sharma (Legal Head) and Sh. Vaibhav Lalit (AR) are present on behalf of the promoter and states that regarding the complaint filed by M/s Karma Lakeland, a public disclaimer notice regarding issuance of any advertisement has been published and a police complaint against the concerned broker has also been lodged. Further, the affidavit through its director for not making any sale/booking in respect of the units falling under ROW of 66 KV HT line till its shifting by HSIIDC alongwith the original bank undertaking will be submitted in the Authority today. The services to the site are to be provided by HSIIDC as a site forms part of the township project and all external services are to be provided and managed by HSIIDC. The promoter shall submit a DD/BG of Rs. 25 lakhs as a security amount in lieu of submission of Fire Scheme approval within 4 months. The promoter shall submit the mining permission before start of construction. Sh. Sandeep Trehan (AR) is present on behalf of the complainants and states that M/s Karma Lakeland has now no further issue regarding the complaint dated 28.08.24  as a public notice as well as undertaking has been submitted and necessary legal action is being taken against the broker who issued advertisement for sale without any authorization. As proposed, the grant of registration is approved subject to submission of BG/DD of Rs 25 lakhs alongwith rectification of the above mentioned deficiencies. The Registration certificate shall be issued after the submission of above along with necessary corrections in online form A-H and DPI. APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
30-Sep-2024 The matter to come up on 07.10.2024. ADJOURNMENT View Order
16-Sep-2024 Sh. Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Vaibhav Lalit (Legal Manager) is present on behalf of the promoter and states that two undertakings have been submitted today in the registry and NOC of the financial institution i.e. HDFC Capital (Vistara) regarding creation of 3rd party rights in respect of the units. The AR further states that the clarification along with the details of the specific units which are affected by two HT lines of 66 KV which are to be shifted by HSIIDC and an undertaking will also be submitted that the promoter shall not advertise, market or sell the units in the towers under the HT lines. Further, regarding the provisioning of services, HSIIDC vide letter dated 25.04.2024 has intimated that water and sewerage connection etc. will be supplied after completion of infrastructure services expected up to 30.04.2026. The promoter also to clarify the provisioning of these services till the same are provided by HSIIDC as no firm dates have been committed by HSIIDC. The matter to come up on 30.09.2024. ADJOURNMENT View Order
02-Sep-2024 The matter is adjourned and to come up on 16.09.2024.  EXAMINATION BY AUTHORITY View Order