17-Mar-2025 |
Ar. Neeraj Gautam,
Associate Architectural Executive and Ms. Asha, Chartered Accountant briefed
about the facts of the project.
Sh. Mohit Adhana
(AR) and Sh. Abhay Jain (Advocate) are present on behalf of the promoter.
The registration
of the project is approved as proposed. The
registration certificate shall be issued after corrections in form REP-I, DPI
and draft BBA of the project. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
10-Mar-2025 |
Ar. Neeraj Gautam,
Associate Architectural Executive and Ms. Asha, Chartered Accountant briefed
about the facts of the project.
Sh. Rishabh Jain
(Advocate) is present on behalf of the promoter and seeks one week’s time to
submit the remaining deficiencies.
The matter to
come up on 17.03.2025. |
ADJOURNMENT |
View Order |
17-Feb-2025 |
Ar. Neeraj Gautam,
Associate Architectural Executive and Ms. Asha, Chartered Accountant briefed
about the facts of the project.
Sh. Rishabh Jain
(Advocate) is present on behalf of the promoter and states that reply has been
submitted on 11.02.2025. However, there are still deficit documents and AR
seeks two weeks’ time for their rectification along with clarification reg.
electric load availability of the colony. The concerned PE to visit the site
and submit the report of the development works completed in the colony.
The matter to
come up on 10.03.2025. |
ADJOURNMENT |
View Order |
20-Jan-2025 |
The matter is adjourned and to come up on 17.02.2025. |
ADJOURNMENT |
View Order |
06-Jan-2025 |
Due to gazetted holiday, the matter is adjourned and to come up on 20.01.2025. |
EXAMINATION BY AUTHORITY |
View Order |