| 18-Nov-2024 |
Ms.
Prachi Singh, Planning Executive briefed about the facts of the project. Sh.
Vedant Batra (AR) is present on behalf of the promoter.
The
AR states that revalidation of the building plans is not required as OC after
completing the construction has already been obtained in respect to all the 180
units registered under the above project and copy of the OC has been already submitted in the registry on
12.11.2024.
Approved
as proposed. The office to check and confirm the same along with rectification
of other deficiencies before issuance of extension of the registration. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
| 21-Oct-2024 |
The matter is adjourned and to come up on 18.11.2024. |
ADJOURNMENT |
View Order |
| 16-Sep-2024 |
The matter is adjourned and to come up on 21.10.2024. |
ADJOURNMENT |
View Order |
| 12-Aug-2024 |
Ms. Prachi Singh, Planning
Executive briefed about the facts of the project.
Sh. Vedant Batra (AR) is present on
behalf of the promoter and requests for 4 weeks time for submission of
revalidated building plan.
The matter to come up on
16.09.2024.
|
ADJOURNMENT |
View Order |
| 22-Jul-2024 |
The matter is adjourned and to come up on 12.08.2024. |
ADJOURNMENT |
View Order |
| 08-Jul-2024 |
The matter is adjourned and to come up on 22.07.2024. |
ADJOURNMENT |
View Order |
| 24-Jun-2024 |
The matter is adjourned and to come up on 08.07.2024. |
EXAMINATION BY AUTHORITY |
--- |