| 08-Jul-2024 |
Ms. Nikita Mittal, Planning Executive
and Sh. Ashish Dubey briefed about the facts of the project.
Sh. Sandeep Tyagi (AR) is present on
behalf of the promoter.
The AR states that the
construction/development works have been completed and OC will be applied
within next 2-4 weeks. The approved service plan and estimates have already
been submitted along with corrected bank undertaking. The AR assures that the
project will be completed and handed over within the period being requested for
extension i.e. 29.06.2025.
In view of the above, approved as
proposed. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
| 03-Jun-2024 |
Sh. Shashank Sharma, Associate Engineer
Executive and Sh. Ashish Dubey briefed about the facts of the project.
None is present on behalf of the promoter. The
promoter is directed to rectify the pending deficiencies along with the renewal
of license.
The matter to come up on 08.07.2024. |
ADJOURNMENT |
--- |
| 27-May-2024 |
The matter is adjourned and to come up on 03.06.2024 |
ADJOURNMENT |
View Order |
| 29-Apr-2024 |
Sh. Shashank Sharma, Associate Engineer
Executive and Ms. Suruchi Pandey briefed about the facts of the project.
Sh. Sandeep Tyagi (AR) is present on behalf of
the promoter and seeks two weeks time for submission of the deficit documents.
The matter to come up on 27.05.2024. |
EXAMINATION BY AUTHORITY |
View Order |