Comprehensive Project Details (Project Extension)
Project Location Details (Project Extension)
Project Name Project Location Project District Project Tehsil Promoter Name
COBAN RESIDENCES Garhi Harsaru Road Village Gopalpur, Sector 99A, Gurugram, Haryana GURUGRAM Pareena Infrastructures Pvt. Ltd.
Project Detail
Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks
RERA-GRG-1623-2024 23-Apr-2024 23-Apr-2024 EXTENSION APPROVED NOT REQUIRED Yes 07-May-2024 By hand Deficiency notice
First hearing
Project Listing Details (Project Extension)
Date of Hearing Proceedings of the day Status Order
18-Nov-2024 Ms. Prachi Singh, Planning Executive briefed about the facts of the project.  Sh. Pardeep Kumar (AR) is present on behalf of the promoter The AR states that revalidation of building plan has been granted by DTCP and renewal letter shall be submitted within three days. The license renewal is already obtained and submitted. The deficit fee has already deposited. Approved as proposed. The office to confirm and ensure rectification of deficiencies before the grant of extension of registration certificate.  EXTENSION APPROVED View Order
21-Oct-2024 The matter is adjourned and to come up on 18.11.2024. ADJOURNMENT View Order
16-Sep-2024 The matter is adjourned and to come up on 21.10.2024. ADJOURNMENT View Order
12-Aug-2024 Ms. Prachi Singh, Planning Executive briefed about the facts of the project. Sh. Pardeep Kumar (AR) is present on behalf of the promoter and requests for 4 weeks time for submission of renewed license and revalidated building plan. The matter to come up on 16.09.2024.  ADJOURNMENT View Order
22-Jul-2024 The matter is adjourned and to come up on 12.08.2024. ADJOURNMENT View Order
03-Jun-2024 Ms. Prachi Singh, Planning Executive briefed about the facts of the project. Sh. Praveen Kumar (AR) and Sh. Kamal Kant Soni (AR) are present on behalf of the promoter. The AR of the promoter seeks six weeks time to submit the deficit documents including deficit fees and renewed license. The matter to come up on 22.07.2024. ADJOURNMENT View Order
27-May-2024 The matter is adjourned and to come up on 03.06.2024 ADJOURNMENT View Order
13-May-2024 Ms. Prachi Singh, Planning Executive briefed about the facts of the project. Sh. Parveen Soni (AR) of the promoter is present on behalf of the promoter. The AR of the promoter seeks one week time to rectify the deficiencies. The matter to come up on 27.05.2024. The director/CEO/Project-Incharge of the promoter company is directed to be present on the next date of hearing.   EXAMINATION BY AUTHORITY View Order