| 11-Feb-2025 |
Ms. Nikita Mittal, Planning
Executive and Sh. Ashish Dubey, Chartered Accountant
briefed about the facts of the project.
Mohd. Hissamuddin (AR) and Sh. Kuldeep (AR) are
present on behalf of the promoter and states that CC in respect of the project
has been received from the DTCP on 17.09.2024 while the instant application
seeking one year extension was already made on 22.03.2024.
Approved as proposed. |
EXTENSION APPROVED |
View Order |
| 10-Feb-2025 |
The matter is adjourned and to come up on 11.02.2025 at 03:00 PM. |
ADJOURNMENT |
--- |
| 27-Jan-2025 |
The matter is adjourned and to come up on 10.02.2025. |
ADJOURNMENT |
--- |
| 23-Dec-2024 |
The matter is adjourned and to come up on 27.01.2025. |
ADJOURNMENT |
--- |
| 25-Nov-2024 |
The matter is adjourned and to come up on 23.12.2024. |
ADJOURNMENT |
--- |
| 28-Oct-2024 |
The matter is adjourned and to come up on 25.11.2024. |
ADJOURNMENT |
--- |
| 07-Oct-2024 |
The matter is adjourned and to come up on 28.10.2024. |
ADJOURNMENT |
--- |
| 09-Sep-2024 |
Ms. Nikita Mittal, Planning
Executive and Sh. Ashish Dubey, Chartered Accountant
briefed about the facts of the project.
Mohd. Hissamuddin (AR) and Sh. Rishi Kapoor
(Advocate) are present on behalf of the promoter.
The AR of the promoter seeks three weeks time
to rectify the deficiencies. The Counsel for the respondent clarifies that the
project had two phases and there is no moratorium proceeding in respect of this
particular phase measuring 2.825 acres and the NEC in respect of this land
shall be submitted after removal of the attachment order of the District
Collector.
The matter to come up on 07.10.2024. |
ADJOURNMENT |
View Order |
| 02-Sep-2024 |
The matter is adjourned and to come up on 09.09.2024. |
ADJOURNMENT |
--- |
| 29-Jul-2024 |
Ms. Nikita Mittal, Planning
Executive and Sh. Ashish Dubey, Chartered Accountant
briefed about the facts of the project.
Mohd.
Hisamuddin (AR) and Sh. Purushottam Tiwari are present on behalf of the
promoter.
The
promoter has filed an application to allow Sh. Rishi Kapoor, Advocate in order
to explain the intricacies involved in the order passed by NCLT as the above
project is not covered under CIRP proceedings. The request is allowed. The
respondent is directed to file reply to the deficiencies already conveyed along
with requisite documents and status of development works completed in the
project so far. The promoter is directed to clarify the queries/shortcomings in
the QPR to the quarter December, 2013 within a period of 2 weeks.
The
matter to come up on 02.09.2024. |
ADJOURNMENT |
View Order |
| 24-Jun-2024 |
Ms.
Nikita Mittal, Planning Executive and Sh. Ashish Dubey, Chartered
Accountant briefed about the facts of the project.
Sh.
Purshottam Tiwari (AR) and Mohd. Hillamuddin (AR) present on behalf of the
promoter and is submitting the latest order passed by NCLT. The matter to be
examined in view of the same.
The
matter to come up on 29.07.2024. |
ADJOURNMENT |
View Order |
| 20-May-2024 |
Sh.
Sumeet, Engineering Officer and Ms. Suruchi Pandey, Chartered Accountant
briefed about the facts of the project.
Shri
Mohd Hissamuddin, AR is present on behalf of the promoter.
The
reply to the deficiency notice has been submitted on 16.5.2024 and AR seeks
four weeks’ time for submission of annual financial statement and a few other
deficiencies.
Matter
to come up on 24.06.2024. |
ADJOURNMENT |
View Order |
| 22-Apr-2024 |
Sh.
Sumeet, Engineering Officer and Sh. Ashish, Chartered Accountant briefed about
the facts of the project.
Mohd.
Hassamuddin (AR) is present on behalf of the promoter.
The deficiency notice was dispatched recently on 19.04.2024. The
promoter is hereby directed to submit the reply to the deficiency notice and
clarify the exact status of case pending before NCLAT since 17.10.2023.
The
director/CEO/Project-Incharge of the promoter company is directed to be present
on the next date of hearing.
The
matter to come up on 20.05.2024. |
EXAMINATION BY AUTHORITY |
View Order |