| 10-Jun-2024 |
Ms.
Prachi Singh, Planning Executive briefed about the facts of the project. Sh.
Ashok Jaunapuria (AR), Sh. Manoj Shukla (AR) and Sh. Sunil Shekhawat (AR) are
present on behalf the promoter.
The AR states that renewal of
license has been obtained and along with revalidated building plans have been
submitted in the registry on 07.06.2024 along with other deficit documents. In
view of the same the proposal for grant of extension under section 6 of the Act
is being granted subject to verification of all deficit documents by the
office.
Approved as proposed. |
EXTENSION APPROVED |
View Order |
| 20-May-2024 |
Sh.
Sumeet, Engineering Officer and Ms. Suruchi Pandey, Chartered Accountant
briefed about the facts of the project.
S/Shri
Ashok Singh Jaunapuria, Manoj Shukla and Sunil Shekhawat are present on behalf
of the promoter.
The
AR of the promoter company requests for three weeks’ time for completing the
deficiencies. The same is allowed.
Matter
to come up on 10.6.2024. |
ADJOURNMENT |
View Order |
| 22-Apr-2024 |
Sh.
Sumeet, Engineering Officer and Sh. Ashish, Chartered Accountant briefed about
the facts of the project.
Sh.
Manoj Shukla (AR) and Sh. Sunil Shekhawat (AR) are present on behalf of the
promoter.
The deficiency notice was dispatched recently on 19.04.2024.
The promoter is hereby directed to submit the reply to the deficiency
notice. Further, the concerned EO to
visit the site of the project and submit the report.
The
director/CEO/Project-Incharge of the promoter company is directed to be present
along with the authorized representative of the landowner companies along with
board resolution on the next date of hearing.
The
matter to come up on 20.05.2024. |
EXAMINATION BY AUTHORITY |
View Order |