15-Jul-2024 |
Ms.
Deepika, Planning Executive
and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case.
Sh. Charan Das (AR), Sh.
Narayan Bhadana (AR), and Sh. Raj Kumar
Singh (AR) are present on behalf of the promoter.
The AR clarifies that the
site is having access from 24 mtr wide road and the list of share of units
between the collaborator and the developer has been signed by both and submitted
in the registry along with corrected format of BBA. The AR seeks three months
time for submission of EC clearance, fire NOC and service plan estimates which
have already been submitted to the concerned authority and their approval is
awaited.
Approved as proposed subject
to submission of BG/DD of Rs. 25 lakh each for the submission of above
clearance within three months. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
01-Jul-2024 |
Ms.
Deepika, Planning Executive
and Ms. Suruchi Pandey, Chartered Accountant briefed about the facts of the
case.
Sh. Charandas (AR), Sh. Ashish
Verma (AR), Sh. Akash Sharma (AR) and Ms. Mallika Arjun Deo (AR) are present on
behalf of the promoter.
The AR seeks 2 weeks’ time to
remove the deficiencies including submission of unit sharing plan duly signed
by the collaborator/land owner, clarity regarding access to the site and
submission of BBA as prescribed under the Rules.
The matter to come up on
15.07.2024 for rectification of above deficiencies. |
ADJOURNMENT |
--- |
10-Jun-2024 |
Ms. Deepika, Planning Executive and Ms. Suruchi Pandey,
Chartered Accountant briefed about the facts of the case.
Sh. Charan Dass (AR) and Sh. Ramesh Bisht (AR) are
present on behalf of the promoter and states that deficit documents have been
submitted on 07.06.2024 which be examined by the office. The AR to also submit
the copy of public notice issued as the license for the group housing has been
obtained after migration from earlier DDJAY scheme wherein no sale or
advertisement was made. The clear no lien certificate for proof of
non-encumbrance of the project land needs to be submitted.
The matter to come up on 01.07.2024. |
ADJOURNMENT |
View Order |
27-May-2024 |
Sh.
Ashish Kush, Planning
Executive and Ms. Suruchi Pandey, Chartered Accountant briefed about the facts
of the case.
Sh.
Charan Das (AR) is present on behalf of the promoter.
The
AR of the promoter seeks two weeks’ time for rectification of remaining
deficiencies. A ten days public notice for inviting objections be published in
two newspapers (1English and 1 Hindi), if any. The land owners shall
be present on the next date of hearing.
The
matter to come up on 10.06.2024. |
ADJOURNMENT |
View Order |
13-May-2024 |
Sh.
Ashish Kush, Planning
Executive and Ms. Suruchi Pandey, Chartered Accountant briefed about the facts
of the case.
Sh.
Charan Das (AR) is present on behalf of the promoter. The AR of the promoter
seeks one week time to rectify the deficiencies.
The
matter to come up on 27.05.2024.
The land owner shall be present on the next date of hearing. |
EXAMINATION BY AUTHORITY |
View Order |