27-May-2024 |
Sh.
Ashish Kush, Planning Executive and Ms. Suruchi Pandey, Chartered Accountant
briefed about the facts of the case.
Sh. C.M. Batra (Sr.GM) on behalf of the promoter, Sh. Ajay Yadav (Land
Ownr), Sh. J.N. Yadav (Land Owner) are present.
The
promoter has submitted two BG of Rs 25 lakhs each for submission of Environment
Clearance and Fire Scheme approval within four months from the grant of
registration. No objection in respect of the public notice issued by the office
has been received till date. The final approval of Service plan & Estimates
shall be submitted within three months from the grant of registration for which
BG has already been submitted to the DTCP, Haryana. The promoter shall submit
the Mining permission before start of construction. In view of the same,
approved as proposed and office to ensure necessary correction in form A to H
and DPI. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
13-May-2024 |
Sh.
Ashish Kush, Planning Executive and Ms. Suruchi Pandey, Chartered Accountant
briefed about the facts of the case.
Sh.
C.M. Batra (SGM Legal & land) on behalf of the promoter and Sh. Ajay Yadav
(Land Owner), Sh. Vijay Singh (Land Owner) are present.
The
promoter to issue a public notice for no sale in respect of earlier license by
the developer inviting objections if any. Further the revenue sharing given in
collaboration agreement be reconciled with the sharing shown in DPI and to be
in consonance with provisions of section 4(2)(l)(D) of the Act of 2016 and a
disclosure be made in the DPI with respect to the circle rate of the land and
calculation of land cost taken in DPI.
The
matter to come up on 27.05.2024. The representative of M/s Logic Soft shall
also be present on the next date of hearing. |
ADJOURNMENT |
View Order |
22-Apr-2024 |
Sh.
Ashish Kush, Planning Executive and Ms. Suruchi Pandey, Chartered Accountant
briefed about the facts of the case.
Sh. Nitin Kohli (AR) is present on behalf of the promoter.
The AR of the promoter states that an advertisement has been published on
18.04.2024 in three newspapers with regard to migration of license No. 06 of
2018 dated 05.01.20218 which was granted for IT Park to Mixed land use vide
license No. 91 of 2023, dated 21.04.2023 inviting objections within a period of
10 days. So far, as the submission of EC, Fire scheme, Service plans and
estimates, BG of Rs. 25 lakhs each shall be submitted in lieu of timely
submission of the compliances as may be specified by the authority.
The
director/CEO/Project-Incharge of the promoter company is directed to be present
along with the landowners on the next date of hearing.
The matter to come up on 13.05.2024. |
EXAMINATION BY AUTHORITY |
View Order |