18-Mar-2024 |
Ms.
Prachi Singh, Planning Executive briefed about facts of the project.
Sh.
Vipul Kumar Dahiya (AR) is present on behalf of the promoter.
Approved
as proposed as the promoter has submitted requisite NOC from the financial
institution i.e. IDBI Trusteeship services Ltd. and the building plans in
respect of above nine plots with stilt + 4 floors stand approved on 17.02.2023
prior to the order of DTCP keeping in abeyance the provision of stilt + 4
floors. The corrections in form A to H and DPI shall be made today. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
--- |
11-Mar-2024 |
Ms. Prachi Singh, Planning
Executive briefed about the facts of the project.
Sh. Vipul Kumar Dahiya (AR)
is present on behalf of the promoter.
The promoter is required to
submit an NOC from Bank with respect to no lien on these particular units
before application is further considered.
The matter to come up on
18.03.2024. |
ADJOURNMENT |
--- |
26-Feb-2024 |
Ms. Prachi Singh
(Planning Executive) briefed about the facts of the case.
Sh.
Vipul Dhaiya (AR) is present on the behalf of the promoter.
The
office has scrutinized the application for registration of the project and the
deficiency notice is yet to be dispatched. The concerned official to dispatch
the notice today itself.
The
matter to come up on 11.03.2024. |