| 18-Mar-2024 |
Sh.
Ashish Kush, Planning Executive and Ms. Ashish Dubey, Chartered Accountant
briefed about the facts of the case.
Sh.
Abhijeet Singh, CEO, Sh. Manik Sharma (AR) and Sh. Bharat Vigmal (AR) are
present on behalf of the promoter.
Approved
as proposed subject to submission of DD/BG of Rs. 25 lakhs each as a security
amount for submission of Approved service plan estimates, Fire scheme approval
and EC within four months. The AR
further states that the construction will be completed and OC obtained within
six years while completion of the project including all the amenities shall be
completed within the date specified in the DPI. The road access permission will
be submitted within three months and condition to this effect will be
incorporated in the RC. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |