Comprehensive Project Details (Project Extension)
Project Location Details (Project Extension)
Project Name Project Location Project District Project Tehsil Promoter Name
HERO HOMES SECTOR-104, DHANWAPUR, GURUGRAM GURUGRAM VIKAS PARK PVT LTD
Project Detail
Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks
RERA-GRG-1537-2024 16-Jan-2024 16-Jan-2024 EXTENSION APPROVED NOT REQUIRED Yes 27-Feb-2024 By Hand Deficiency Notice
First hearing
Project Listing Details (Project Extension)
Date of Hearing Proceedings of the day Status Order
29-Apr-2024 Ms. Prachi Singh, Planning Executive briefed about the facts of the project. Sh. Deepak Sharma (AR), Sh. Akash Gupta (AR) and Sh. Pratik Gautam (AR) are present on behalf of the promoter. The AR states that the applicant is a BIP holder for 9.053 acres and out of seven towers under the project, the OC in respect of four towers has already been applied to DTCP and construction of remaining three towers is also completed and finishing work is in progress and same shall be completed by the end of 2024. Further, a complaint was received vide dak no. 69728 dated 15.04.2024 against the promoter regarding the alleged illegal construction on proposed green belt. In this regard, the promoter stated that this complaint is not part of the project. The concerned planning executive also confirmed the same on the basis of site visit. The promoter requests to make a correction in the registered area from 9.053 acres to 8.9016 acres mentioned in earlier RC, being an error of fact. So far as the correction of area in the certificate is concerned, a separate application will be made by the promoter along with supporting documents for the same.   In view of the above, the extension requested under Section 6 of the Act, 2016 is approved as proposed.  EXTENSION APPROVED ---
15-Apr-2024 Ms. Prachi Singh, Planning Executive briefed about the facts of the project. Sh. Deepak Sharma (AR), Sh. Akash Gupta (AR) and Sh. Nardev Arya (AR) are present on behalf of the promoter. The AR of the promoter states that construction of the towers (1 to 7) is complete. OC has been applied for tower 1 to 4 and finishing work is underway in towers 5 to 7. The concerned PE to visit the site and submit the updated status report about the completion of works and works which remain for completion. The matter to come up on 29.04.2024. ADJOURNMENT ---
07-Feb-2024 Ms. Prachi Singh (Planning Executive) briefed about the facts of the case. The application submitted by the promoter has been scrutinized by the concerned official, but the deficiency notice has not been dispatched till date. Therefore, in view of the same the matter is adjourned, and the concerned official is directed to dispatch the notice. The next date of hearing will be conveyed after submission of reply of deficiencies. ADJOURNMENT ---
05-Feb-2024 The matter is adjourned to 07.02.2024 at 03:30 PM. EXAMINATION BY AUTHORITY ---