19-Feb-2024 |
Sh.
Ashish Kush, Planning Executive and Sh. Ashish Dubey, Accountant briefed about
the facts of the case.
Sh.
Mandeep Singh Oberoi and Sh. Himanshu Juneja, AR are present on behalf of the
promoter
The
AR of the promoter that the company has applied for RC in respect of the Phase
B approved by DTCP in the Building plans for an area admeasuring 5.41 Acres and
earlier this portion of land was also reserved for future expansion. The OC in
respect of Phase-A admeasuring 15.60 acres already stands obtained on 29.08.2016
before commencement of the Act, 2016. The AR further states that all the
services and facilities of the Phase B shall be independent of the earlier
phase already handed over to the RWA after filing DOD. The environment
clearance has already been recommended by the committee and vide letter dated
23.01.2024, the Member-secretary of SEIAA Haryana has conveyed to consider the
approval after appointment of chairperson of SEIAA, Haryana. In view of the same, the authority grants
four months’ time for submission of approved Environment Clearance failing
which the penal proceedings including freezing of accounts shall be initiated.
The Re-validated Mining permission shall also be submitted before start of
excavation/construction.
Approved
as proposed. |