| 20-May-2024 |
Shri Parvin Kumar, Vishal Mohan Sharma and Paras Gupta are present on
behalf of the promoter and states that out of 7 towers in the project, the OC
in respect of three towers has already been obtained and possession also handed
over to the allottees. Further, the construction
of remaining four towers has also been completed and final finishing work is in
progress which shall also be completed within one year of extension including
obtaining of OC from DTCP. In view of
same, request for extension is granted subject to rectification of the deficit
documents and EC renewal shall also be submitted in next three months.
|
EXTENSION APPROVED |
--- |
| 29-Apr-2024 |
Ms.
Prachi Singh, Planning Executive briefed about the facts of the project.
Sh.
Pravin Kumar (AR), Paras Gupta (AR) and Sh. Vishal Mohan (AR) are present on
behalf of the promoter.
The
AR of the promoter seeks two weeks time for submission of the deficit documents
already conveyed.
The
matter to come up on 20.05.2024. |
ADJOURNMENT |
--- |
| 15-Apr-2024 |
Ms. Prachi Singh, Planning Executive briefed about the
facts of the project.
Sh.
Rohit Bhatnagar (AR), Sh. Paras Gupta (AR) and Sh. Vishal Mohan (AR) are
present on behalf of the promoter.
The
promoter is directed to comply with the deficiencies informed to them. The
concerned PE to visit the site and submit the updated status report about the
completion of works.
The
matter to come up on 29.04.2024. |
ADJOURNMENT |
--- |
| 01-Apr-2024 |
Ms. Prachi Singh Planning Executive briefed about the facts
of the project.
Sh. Rohit Bhatnagar (AR), Sh. Paras Gupta (AR) and Sh. Vishal
Mohan (AR) are present on behalf of the promoter.
The
Bank account details are mismatched in QPR & CA certificate submitted by
the promoter.
The promoter to explain on the next date of hearing and submit reply to
deficiency letter issued to the promoter.
The matter to come up on 15.04.2024. |
ADJOURNMENT |
--- |
| 15-Jan-2024 |
Ms. Prachi Singh Planning Executive briefed about the
facts of the project.
No
reply has been submitted by the promoter company against the deficiencies
conveyed by the authority through deficiency notice dated 12.01.2024.
Therefore, in view of the same the matter is adjourned, and the next date of
hearing will be conveyed after submission of reply of deficiencies already
conveyed.
Further,
if no response is received from the promoter within next 4 week’s time, in that
case the concerned official to put up the matter on file for issuance of show
cause notice as to why their application for extension of registration of
project may not be rejected following the due procedure under the Act of 2016. |