03-Jun-2024 |
Ms. Prachi
Singh, Planning Executive briefed about the facts of the project.
Sh. Abhijeet Singh (AR) and
Bharat (Authorized Signatory) are present on behalf of the promoter.
The AR of the promoter states that they have applied
for the
supersession of earlier registration certificate no. 05 of 2023 after issuance
of revised land schedule of 24.74375 acres in licence no. 195 of 2022 by DTCP.
The area
measuring 0.68125 acres under collaboration in the
land falling in the current application is marked frozen
by the DTCP for the
purpose
of
sale of plots
till the said land is either purchased by M/s Loon Land Development Ltd. or execution of registered collaboration
agreement with the landowners / land owning company. The promoter submits that the sale deed
for the remaining area measuring 24.0625 acres falling under current
application
has been executed in the favor of promoter,
i.e., M/s Loon Land Development Ltd.
Further, the promoter states
that
the
entry
in
revenue record w.r.t 24.74375 acres
has been made and a copy will be submitted
to the
Authority.
The
promoter has submitted consent of 444 out of 635 allottees of the project registered vide RC no.06 of 2023 as independent floors over the already registered
plots with
regard to change in the layout plan of the project which is more than 2/3rd required. A Public notice inviting objections w.r.t the same was published in
the Tribune
and Dainik Tribune dated 15.05.2024 and no objection has been received in the Authority.
Further,
the date of completion of project declared by the promoter under Section 4(2)(l)(C) of the Act of 2016 and the conditions of the allotment will remain the same.
Keeping
in view the above, the Authority decides to
supersede the earlier registration certificate no. 06 of 2023 dated 12.01.2023 subject to the
condition that the area
measuring
0.68125 acres
under
collaboration in the land falling
in the current application will remain frozen for the purpose of sale of plots till the said Iand is either purchased by M/s Loon
Land Development
Ltd. or execution of registered
collaboration
agreement with the landowners / land owning company and correction in the requisite form in REP-I and DPI. This shall be without prejudice to the rights
of the allottees under
section 14
and 18 of the Act,2016. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
13-May-2024 |
Ms. Prachi Singh, Planning Executive briefed
about the facts of the project.
Sh. Abhijeet Singh (AR) and Sh. Bharat Vigmal
(AR) are present on behalf of the promoter.
The public notice for 15 days inviting
objections regarding the consent of 2/3rd allottees with respect to the
revision in layout plan submitted by the promoter to be issued in at least two
prominent newspapers of local circulation (one English and one Hindi).
The landowners of the project are directed to
be present on the next date of hearing.
The matter to come up on 03.06.2024. |
ADJOURNMENT |
--- |
22-Apr-2024 |
Ms. Prachi Singh, Planning Executive
briefed about the facts of the project.
None
is present on behalf of the promoter.
The
director/CEO/Project-Incharge of the promoter company is directed to be present
along with the landowner/ authorized representative of the landowner companies
along with board resolution on the next date of hearing.
The matter to come up on
13.05.2024. |
ADJOURNMENT |
--- |
15-Jan-2024 |
Ms. Prachi Singh Planning Executive briefed about the
facts of the project.
No
reply has been submitted by the promoter company against the deficiencies
conveyed by the authority through deficiency notice dated 12.01.2024.
Therefore, in view of the same the matter is adjourned, and the next date of
hearing will be conveyed after submission of reply of deficiencies already
conveyed.
Further,
if no response is received from the promoter within next 4 week’s time, in that
case the concerned official to put up the matter on file for issuance of show
cause notice as to why their application for registration of project may not be
rejected following the due procedure under the Act of 2016. |
EXAMINATION BY AUTHORITY |
View Order |