Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
ELAN IMPERIAL Village- Nakhnoula, Sector-82, Gurugram GURUGRAM Manesar Elan Imperial Pvt Ltd (Formerly known as Ambience Infrastructure Developers Pvt Ltd)
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/788/520/2024/15 DATED 21.02.2024 RERA-GRG-1508-2023 12-Dec-2023 11-Dec-2023 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 28-Dec-2023 Online and by hand Deficiency notice
First hearing View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/788/520/2024/15 DATED 21.02.2024 19-Jun-2024 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
19-Feb-2024 Sh. Sumeet Choudhary is present on behalf of the promoter. The AR of the promoter states that they are submitting the deficit fee including late fee and simultaneously request to consider the representation to waive off the late fee as the building plans and other statutory approvals are obtained or being obtained recently except licenses and zoning plan approval. The authority decides that the representation submitted by the promoter be put up on file along with AG opinion obtained in other such cases for taking the decision by the authority regarding applicability of late fee on the project registration application.   The AR further states that fire scheme approval and service plan estimate approval is applied and the same will be submitted within 3 months from issuing RC for which the BG amounting Rs 25 lakh each are also being submitted in the authority. The environment clearance has already been recommended by the committee and vide letter dated 23.01.2024, the Member-secretary of SEIAA Haryana has conveyed to consider the approval after appointment of chairperson of SEIAA, Haryana.  In view of the same, the authority grants four months’ time for submission of approved Environment Clearance failing which the penal proceedings including freezing of accounts shall be initiated. Further, the site of the project exists on 12 mt service road for which the access permission is not required, and the mining permission will be obtained and submitted before start of excavation/construction. The balance deficit documents will also be submitted within two days after making necessary corrections. In view of the above the Authority decides to grant the registration certificate. The RC shall be issued after submission of deficit documents. APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
12-Feb-2024 Sh. Sumeet, Engineering Officer and Sh. Ashish, Chartered Accountant briefed about the facts of the case. Shri S. Chaudhary (Head-Business Department) is present on behalf of the promoter. The AR of the promoter requests for one week’s time to submit the remaining documents. Request is allowed.   Matter to come up on 19.02.2024. ADJOURNMENT View Order
01-Jan-2024 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. No reply has been submitted by the promoter company against the deficiencies conveyed by the authority through deficiency notice dated 28.12.2023. Therefore, in view of the same the matter is adjourned, and the next date of hearing will be conveyed after submission of reply of deficiencies already conveyed. Further, if no response is received from the promoter within next 4 week’s time, in that case the concerned official to put up the matter on file for issuance of show cause notice as to why their application for registration of project may not be rejected following the due procedure under the Act of 2016. EXAMINATION BY AUTHORITY View Order