07-Feb-2024 |
Sh. Shashank Sharma, Associate Engineer Executive
briefed about the facts of the project.
Sh. Anurag Srivastava (AR) and Sh. Vedant
Batra (Company Secretary) are present on behalf of the promoter.
The AR states that the requisite BG has been
submitted to DGTCP for final approval of service plans and estimates as CE/HSVP
has conveyed its technical approval to DTCP. The mining permission shall be
obtained before start of excavation at site and seeks six month time for
submission of environmental clearance which is already applied to the concerned
authority. Approved as proposed subject to submission approved service plans
and estimates from DTCP within three months and EC within six months failing
which the authority shall be constrained to initiate the legal action including
freezing of bank accounts. Besides above condition a BG/DD of Rs. 25 Lakh may
be obtained. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
--- |
05-Feb-2024 |
The matter is adjourned to 07.02.2024 at 03:30 PM. |
ADJOURNMENT |
--- |
29-Jan-2024 |
Sh. Shashank Sharma, Associate Engineer
Executive and Sh. Ashish Dubey briefed about the facts of the project.
Sh. Aurag Srivastava (GM) and Sh. Naveen Kumar
(Architect) are present on behalf of the promoter.
The approval of EC is pending with SEIAA. The
promoter to ascertain the exact status of the case from the Committee and
revert on 05.02.2024.
The matter to come up on 05.02.2024. |
ADJOURNMENT |
--- |
08-Jan-2024 |
No
reply has been submitted by the promoter company against the deficiencies
conveyed by the authority through deficiency notice dated 02.01.2024.
Therefore, in view of the same the matter is adjourned, and the next date of
hearing will be conveyed after submission of reply of deficiencies already
conveyed.
Further,
if no response is received from the promoter within next 4 week’s time, in that
case the concerned official to put up the matter on file for issuance of show
cause notice as to why their application for registration of project may not be
rejected following the due procedure under the Act of 2016. |
EXAMINATION BY AUTHORITY |
View Order |