| 20-May-2024 |
Ms.
Prachi Singh, Planning Executive briefed about the facts of the project.
S/Shri
Ashok Singh Jaunapuria, Manoj Shukla and Sunil Shekhawat are present on behalf
of the promoter.
The
AR states that the units have already been constructed and completed at
site. The OC is being applied in respect
of the units and all other services are already available. The minor deficiencies in the financial
details shall be rectified. In view of
the same, approved as proposed and one year extension is being granted for
completion of the project. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
--- |
| 13-May-2024 |
Ms.
Prachi Singh, Planning Executive briefed about the facts of the project.
Sh.
Ashok Jaunapuria (Directors) and Sh. Sunil Shekhawat (AR) are present on behalf
of the promoter.
Reply has been submitted on 09.05.2024 which needs to be scrutinized.
The matter to come up
on 20.05.2024. |
ADJOURNMENT |
--- |
| 22-Apr-2024 |
Ms.
Prachi Singh, Planning Executive briefed about the facts of the project.
Sh.
Manoj Shukla (AR) and Sh. Sunil Shekhawat (AR) are present on behalf of the
promoter.
The
concerned PE to visit the site and verify the facts.
The director/CEO/Project-Incharge
of the promoter company is directed to be present along with the authorized
representative of the landowner companies along with board resolution on the
next date of hearing.
The
matter to come up on 13.05.2024. |
ADJOURNMENT |
--- |
| 18-Dec-2023 |
The matter to come up on 22.04.2024. |
EXAMINATION BY AUTHORITY |
View Order |