11-Mar-2024 |
Sh.
Ashish Kush, Planning Executive briefed about the facts of the case.
Sh.
Jatin Arora (AR), Sh. Haridesh Bedi (AR) and Sh. Ravi Gautam (AR) are present
on behalf of the promoter.
The
promoter has declared the date of completion as 30.06.2028 as building plans
approved for the site are valid upto 10.01.2029 and renewal of license shall be
taken after its expiry on 14.06.2027. The road access permission from PWD road
stand applied on 15.09.2023 and is fixed for approval in today’s meeting. The
BG/DD for submission of Fire scheme approval as well as Service plans & estimates
of Rs. 25 lakhs each as a security amount has been deposited in the Authority
today and the requisite approvals will be submitted within three months from
grant of registration certificate as the same are already in advance stage of
approval with the competent authority. The promoter will submit DD amounting to
Rs. 25 lakhs for submission of road access permission within three months from
grant of registration certificate.
Approved
as proposed subject to the above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |