Project Name | Project Location | Project District | Project Tehsil | Promoter Name |
---|---|---|---|---|
Smartworld Orchard Street | Sector 61,Gurugram.Haryana | GURUGRAM | Gurgaon | SUPOSHAA REALCON PRIVATE LIMITED |
Project Registration Number | Project Id | Receiving Date | Online Submission Date | Current Status | Next Date of Hearing | Notice Dispatched | Notice Dispatched On | Notice Tracking Id | Notice Dispatched Remarks | View Notice | Initially Scrutinized Remarks | Details of Project(Form A-H) |
---|---|---|---|---|---|---|---|---|---|---|---|---|
GGM/773/505/2023/117 DATED 18.12.2023 | RERA-GRG-1488-2023 | 09-Nov-2023 | 09-Nov-2023 | APPROVED AND CERTIFICATE UPLOADED | NOT REQUIRED | Yes | 30-Nov-2023 | Online | 1st deficiency notice | First hearing | View Form(A-H) |
Project Registration Number | Uploading Date | Remarks | View Certificate |
---|---|---|---|
GGM/773/505/2023/117 DATED 18.12.2023 | 05-Feb-2024 | RC Uploaded |
Date of Hearing | Proceedings of the day | Status | Order |
---|---|---|---|
18-Dec-2023 | Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Abhijeet Singh (AR), Sh. Manik Sharma (AR) and Sh. Bharat Vigmal (AR) are present on behalf of the promoter. Approved as proposed. The AR submits that the extension in respect of the plotted colony for one year has already been applied and that no individual plots has been sold as the promoter has sought registration for floor wise sale of units which is still valid and the above registration is in respect of commercial component of above scheme for which approval has been obtained from the competent authority. The AR undertakes to submit the QPRs and annual audited statements under 4(2)(l)(D) failing which penal action for non- submission shall be initiated. | APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS | View Order |
04-Dec-2023 | Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Bharat Vigmal and Anishna Mitra (AR) are present on behalf of the promoter. The AR of the promoter states that the reply to the deficiencies pointed out by the authority will be submitted in one week. The matter is adjourned and to come up on 18.12.2023. | EXAMINATION BY AUTHORITY | View Order |