| 29-Jan-2024 |
Sh. Sumeet, Project Coordinator and Sh. Ashish, Chartered Accountant briefed
about the facts of the project.
Sh. Ravi Verma (AR) and Sh. Bipin Bathla (AR) are present on behalf of the
promoter.
Approved as proposed subject to submission of DD of Rs. 25 lakh on account
of penalty for delay in compliance of the time schedule given in the
undertaking under section 4(2)(l)(C). The continuation of the project is being
granted upto 31.12.2024 in the interest of allottees for completion of the
project. This is without prejudice to the rights of the allottees under section
18 of the Act of 2016. The excess fee if any beyond the period of continuation
of the registration be adjusted in the above penalty amount. Further, the
Authority decides to de-freeze the accounts of the project as the application
under section 7(3) is being allowed for a further period upto 31.12.2024. |
CONTINUING APPROVED |
--- |
| 08-Jan-2024 |
Ms. Asha Chartered Accountant briefed about the facts of the case.
Sh. Ravi Varma (AR) is present on behalf of the promoter.
The matter to come up on 29.01.2024. Meanwhile, the planning branch is
directed to conduct site inspection of the project and submit a report within a
period of 10 days. |
ADJOURNMENT |
--- |
| 04-Dec-2023 |
Ms. Asha Chartered Accountant briefed about the facts of the case.
Sh. Ravi is present on behalf of the promoter.
The Promoter states that the reply
has already been submitted on Friday (01.12.2023) which is yet to be
scrutinized. Meanwhile, a
public notice for inviting objections from the allottees be issued in at least
two prominent newspapers including one Hindi as being given in case of
continuation of registration under section 7(3) of the Act of 2016.
The matter to come up on 08.01.2024. |
ADJOURNMENT |
View Order |
| 20-Nov-2023 |
Ms. Asha Chartered Accountant briefed about the facts of the case.
The application
submitted by the promoter has been scrutinized by the concerned official, but
the deficiency notice has not been dispatched till date. In view of the same
the matter is adjourned, and the next date of hearing will be conveyed only
after the submission of replies to the deficiencies conveyed through deficiency
notice. Further, if
no response is received from the promoter within next 4 weeks' time, in that
case the concerned official to put up the matter on file for issuance of show
cause notice as to why their application for registration of project may not be
rejected following the due procedure under the Act of 2016. |
EXAMINATION BY AUTHORITY |
View Order |