Comprehensive Project Details (Project Extension)
Project Location Details (Project Extension)
Project Name Project Location Project District Project Tehsil Promoter Name
SMARTWORLD ORCHARD Sector -61, Gurugram Manesar Urban Complex, Gurugram, Haryana GURUGRAM Suposhaa Realcon Private Limited
Project Detail
Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks
RERA-GRG-1483-2023 02-Nov-2023 02-Nov-2023 EXTENSION APPROVED NOT REQUIRED Yes 16-Nov-2023 Online and by hand Deficiency notice
First hearing
Project Listing Details (Project Extension)
Date of Hearing Proceedings of the day Status Order
04-Aug-2025 Sh. Sumeet, Engineering Officer and Sh. Ashish, Chartered Accountant briefed about the facts of the case. S/Shri Abhijeet Singh, Manik Sharma and Bharat Vigmal are present on behalf of the promoter. The Promoter M/s Suposhaa Realcon Pvt. Ltd. on 31.10.2023, applied for extension of registration of their affordable residential plotted colony under DDJAY namely “Smartworld Orchard” in Sector-61, Gurugram registered with the Authority vide RC No. RC/REP/HARERA/GGM/616/348/2022/91 dated 04.10.2022 and valid up to 31.10.2023. The deficiencies in the application were conveyed to the promoter vide notice dated 16.11.2023 with an opportunity of hearing on 20.11.2023. During hearing dated 20.11.2023, it was noted that no reply has been submitted by the promoter company against the deficiencies conveyed by the authority through notice dated 16.11.2023 and the matter was adjourned, and the next date of hearing to be conveyed after submission of reply of deficiencies already conveyed. Later on, the reply was submitted by the promoter on 14.12.2023 but due to internal work reallocations and other related factors, the next date of hearing was not conveyed to the promoter. Recently, it was noted by the Authority that the matter is pending since 2023 and no date has been fixed for hearing. The Authority decides that the matter to be list for hearing on 04.08.2025. Accordingly, the promoter was intimated the next date of hearing in the instant matter. The promoter further submitted the two more replies dated 24.07.2025 and 30.07.2025 and the same have been scrutinized by the office concerned official. A public notice was also published in three newspapers dated 24.07.2025 for extension of registration of project against which no objections have been received in the Authority and none appeared in person before the Authority today i.e., 04.08.2025. The Authority noted that the time period for which extension under Section 6 of the Act, 2016 has been sought by the promoter, stand lapsed on 30.10.2024. The site of project has also been inspected by the concerned official of the Authority and it is reported that the project site has access from 12 mt service road adjacent to 60 mt wide road fully functional. Further, the promoter is developing the residential floors over all plots and maximum construction has been completed by the promoter along with services like road, water supply, sewer & storm water drains. The AR of the promoter states that they are developing the residential floors over all the plots in the current DDJAY plotted colony and obtained the separate RERA registration for the same & valid till 30.12.2025. Further, the construction of floors on maximum number of plots has already been completed and all the services such as road, water, sewer, storm are completed in that area. The remaining area where floors construction is pending, the services such as sewer, storm have been laid and final road work is to be completed after completion of construction of floors only. The AR of the promoter requests the Authority to consider their application for grant of extension of one year under Section 6 of the Act of 2016 for their affordable residential plotted colony under DDJAY namely “Smartworld Orchard” in Sector-61, Gurugram and further assures the Authority to apply for permission for continuation of registration of project to remain in force under Section 7(3) of the Act of 2016, for further time period till obtaining completion certificate of the project. Keeping in view the above instances, the Authority decides to grant extension of registration of project for one year from expiry of registration of project till 30.10.2024. Further, the promoter will simultaneously apply for continuation of registration of project under Section 7(3) of the Act, 2016. The extension of registration certificate shall be issued after necessary compliances mentioned in Remarks above.  EXTENSION APPROVED View Order
20-Nov-2023 Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha (Chartered Accountant) briefed about the facts of the case. None is present on the behalf of the promoter. No reply has been submitted by the promoter company till 16.11.2023 against the deficiencies conveyed by the authority through notice dated 16.11.2023. Therefore, in view of the same the matter is adjourned, and the next date of hearing will be conveyed after submission of reply of deficiencies already conveyed. Further, if no response is received from the promoter within next 4 weeks’ time, in that case the concerned official to put up the matter on file for issuance of show cause notice as to why their application for extension of registration of project may not be rejected following the due procedure under the Act of 2016.Further the matter has been discussed with the Authority and as per the directions & approval matter is fixed for hearing on 04.08.2025. EXAMINATION BY AUTHORITY View Order