| 04-Aug-2025 |
Sh.
Sumeet, Engineering Officer and Sh. Ashish, Chartered Accountant briefed about
the facts of the case.
S/Shri
Abhijeet Singh, Manik Sharma and Bharat Vigmal are present on behalf of the
promoter.
The Promoter M/s Suposhaa
Realcon Pvt. Ltd. on 31.10.2023, applied for extension of registration of their
affordable residential plotted colony under DDJAY namely “Smartworld Orchard”
in Sector-61, Gurugram registered with the Authority vide RC No.
RC/REP/HARERA/GGM/616/348/2022/91 dated 04.10.2022 and valid up to 31.10.2023.
The deficiencies in the application were conveyed to the promoter vide notice
dated 16.11.2023 with an opportunity of hearing on 20.11.2023.
During hearing dated
20.11.2023, it was noted that no reply has been submitted by the promoter
company against the deficiencies conveyed by the authority through notice dated
16.11.2023 and the matter was adjourned, and the next date of hearing to be
conveyed after submission of reply of deficiencies already conveyed.
Later on, the reply was
submitted by the promoter on 14.12.2023 but due to internal work reallocations
and other related factors, the next date of hearing was not conveyed to the
promoter. Recently, it was noted by the Authority that the matter is pending
since 2023 and no date has been fixed for hearing. The Authority decides that
the matter to be list for hearing on 04.08.2025. Accordingly, the promoter was
intimated the next date of hearing in the instant matter.
The promoter further
submitted the two more replies dated 24.07.2025 and 30.07.2025 and the same
have been scrutinized by the office concerned official. A public notice was
also published in three newspapers dated 24.07.2025 for extension of
registration of project against which no objections have been received in the
Authority and none appeared in person before the Authority today i.e.,
04.08.2025.
The
Authority noted that the time period for which extension under Section 6 of the
Act, 2016 has been sought by the promoter, stand lapsed on 30.10.2024.
The
site of project has also been inspected by the concerned official of the
Authority and it is reported that the project site has access from 12 mt
service road adjacent to 60 mt wide road fully functional. Further, the
promoter is developing the residential floors over all plots and maximum
construction has been completed by the promoter along with services like road,
water supply, sewer & storm water drains.
The
AR of the promoter states that they are developing the residential floors over
all the plots in the current DDJAY plotted colony and obtained the separate
RERA registration for the same & valid till 30.12.2025. Further, the
construction of floors on maximum number of plots has already been completed
and all the services such as road, water, sewer, storm are completed in that
area. The remaining area where floors construction is pending, the services
such as sewer, storm have been laid and final road work is to be completed
after completion of construction of floors only.
The
AR of the promoter requests the Authority to consider their application for
grant of extension of one year under Section 6 of the Act of 2016 for their affordable residential plotted colony
under DDJAY namely “Smartworld Orchard” in Sector-61, Gurugram and further assures the Authority to apply
for permission for continuation of registration of project to remain in force
under Section 7(3) of the Act of 2016, for further time period till obtaining
completion certificate of the project.
Keeping
in view the above instances, the Authority decides to grant extension of
registration of project for one year from expiry of registration of project
till 30.10.2024. Further, the promoter will simultaneously apply for continuation
of registration of project under Section 7(3) of the Act, 2016.
The
extension of registration certificate shall be issued after necessary
compliances mentioned in Remarks above. |
EXTENSION APPROVED |
View Order |