Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
LYKEHOMES AVENUE VILLAGE FARUKHNAGAR , SECTOR 3, GURUGRAM HARYANA GURUGRAM Farrukhnagar LYKEHOMES PRIVATE LIMITED
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/786/518/2024/13 DATED 12.02.2024 RERA-GRG-1466-2023 28-Nov-2023 27-Nov-2023 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 30-Nov-2023 HARERA/GGM/RPIN/679 DISPATCHED TO AR
First hearing View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/786/518/2024/13 DATED 12.02.2024 29-May-2024 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
12-Feb-2024 Ar. Neeraj Gautam (Associate Architectural Executive) and Sh. Ashish Dubey (Chartered Accountant) briefed about the facts of the case. Sh. Pankaj Kumar (AR) is present on behalf of the promoter. The Chief Engineer, HSVP, Panchkula vide memo no.8840 dated 10.1.2024 has conveyed the technical approval of service plans and estimates to the DTCP and in pursuance thereof, the applicant promoter has submitted the BG of Rs.1.14 Crores to DTCP on 5.02.2024 for release of the approved plans and estimates. The AR assures to submit the approved copy in the registry of the authority within 30 days failing which the account of the promoter shall be frozen and the concerned official shall put up the file for orders of the authority. Approved as proposed.  APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
15-Jan-2024 Ar. Neeraj Gautam (Associate Architectural Executive) and Sh. M. L. Sardana (Accountant) briefed about the facts of the case. Sh. Pawan Kumar (AR) is present on behalf of the promoter. The AR submits that approval of zoning plan is in advance stage of approval with DTCP and BG in reference to demand raised CE HSVP is also being submitted to DTCP for approval of service plans and estimates. The AR seeks two weeks’ time for submission of deficit documents. Request is allowed. The matter to come up on 12.02.2024.   ADJOURNMENT View Order
01-Jan-2024 Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha (Chartered Accountant) briefed about the facts of the case. Sh. Pawan Kumar (AR) is present on behalf of the promoter. The AR seeks two weeks time for submission of deficit approvals/documents. The matter to come up on 15.01.2024.  ADJOURNMENT View Order
11-Dec-2023 Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha (Chartered Accountant) briefed about the facts of the case. Sh. Pawan Kumar (AR) is present on the behalf of the promoter. The promoter is directed to submit the rectified bank undertaking, approved zoning plan, non- encumbrance certificate duly certified by a revenue officer not below the rank of Tehsildar and other deficit documents listed above in the Authority. The AR of the promoter seeks two weeks’ time to submit the above-mentioned deficiencies in the Authority. The matter to come up on 01.01.2024. ADJOURNMENT View Order
04-Dec-2023 Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha (Chartered Accountant) briefed about the facts of the case. Sh. Pawan Kumar (AR) is present on the behalf of the promoter. The AR of the promoter states that they have submitted the reply to the deficiency notice in the Authority today. The reply be examined, and status of remaining deficiencies be submitted on the next date of hearing. The matter to come up on 18.12.2023. EXAMINATION BY AUTHORITY View Order