08-Apr-2024 |
Sh. Shashank Sharma, Associate Engineer
Executive and Sh. Ashish, Chartered Accountant briefed about the facts of the
project.
Sh. Inderjeet Singh (AR) and Sh. R.K. Singh
are present on behalf of the promoter.
The AR clarifies that present access to the
site is through a 4 karam (22 Ft wide) as per policy parameters fixed by PSTCP
vide Memo No Misc
– 504/2020-2TCP dated 20.10.2020 and
states that environment clearance already applied to Central Expert Appraisal
Committee of the Environment Ministry
Further, the promoter shall submit the DD/BG
of Rs. 25 lakhs each for submission of approved fire scheme, approved service
plan estimates and environment clearance within 4 months. The promoter shall
further make a declaration regarding the present condition of services to be
provided made in the project in the marketing brochure clarifying that the land
for master road as per approved lay out plan of 2031 AD for Urban Estate Sohna
has not been acquired yet and as such the arrangement for water supply and sewage
disposal shall be made by the promoter at his own level until then. No
sale/booking in respect of the units frozen by DTCP in lieu of EDC till removal
of the lien by DTCP. Approved as proposed. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
--- |
27-Mar-2024 |
Sh. Shashank Sharma, Associate Engineer
Executive and Sh. Ashish, Chartered Accountant briefed about the facts of the
project.
Sh. Inderjeet Singh (AR) is present on behalf
of the promoter.
The AR submits that the reply to the
deficiency notice has been submitted today including the deficit fee which has
been paid through NEFT. The office to examine and submit.
The
matter to come up on 08.04.2024. |
ADJOURNMENT |
--- |
04-Mar-2024 |
Sh. Shashank Sharma, Associate Engineer
Executive briefed about the facts of the project.
Sh.
Inderjeet Singh (AR) is present on behalf of the promoter.
The AR
of the promoter seeks two weeks’ time to comply with the deficiencies.
The
matter to come up on 27.03.2024 at 3.00 PM. |
ADJOURNMENT |
View Order |
19-Feb-2024 |
Sh. Shashank Sharma, Associate Engineer
Executive briefed about the facts of the project.
The
application submitted by the promoter has been scrutinized by the concerned
official, but the deficiency notice has not been dispatched till date.
Therefore, in view of the same the matter is adjourned, and the concerned
official is directed to dispatch the notice. The next date of hearing will be
conveyed after submission of reply of deficiencies. |
EXAMINATION BY AUTHORITY |
View Order |