Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/814/546/2024/41 DATED 15.04.2024 RERA-GRG-1453-2023 29-Jan-2024 06-Oct-2023 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 22-Feb-2024 By hand By hand
First hearing View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/814/546/2024/41 DATED 15.04.2024 13-Jun-2024 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
08-Apr-2024 Sh. Shashank Sharma, Associate Engineer Executive and Sh. Ashish, Chartered Accountant briefed about the facts of the project. Sh. Inderjeet Singh (AR) and Sh. R.K. Singh are present on behalf of the promoter. The AR clarifies that present access to the site is through a 4 karam (22 Ft wide) as per policy parameters fixed by PSTCP vide Memo No Misc – 504/2020-2TCP dated 20.10.2020 and states that environment clearance already applied to Central Expert Appraisal Committee of the Environment Ministry Further, the promoter shall submit the DD/BG of Rs. 25 lakhs each for submission of approved fire scheme, approved service plan estimates and environment clearance within 4 months. The promoter shall further make a declaration regarding the present condition of services to be provided made in the project in the marketing brochure clarifying that the land for master road as per approved lay out plan of 2031 AD for Urban Estate Sohna has not been acquired yet and as such the arrangement for water supply and sewage disposal shall be made by the promoter at his own level until then. No sale/booking in respect of the units frozen by DTCP in lieu of EDC till removal of the lien by DTCP. Approved as proposed.  APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS ---
27-Mar-2024 Sh. Shashank Sharma, Associate Engineer Executive and Sh. Ashish, Chartered Accountant briefed about the facts of the project. Sh. Inderjeet Singh (AR) is present on behalf of the promoter. The AR submits that the reply to the deficiency notice has been submitted today including the deficit fee which has been paid through NEFT. The office to examine and submit. The matter to come up on 08.04.2024. ADJOURNMENT ---
04-Mar-2024 Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. Sh. Inderjeet Singh (AR) is present on behalf of the promoter. The AR of the promoter seeks two weeks’ time to comply with the deficiencies. The matter to come up on 27.03.2024 at 3.00 PM. ADJOURNMENT View Order
19-Feb-2024 Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. The application submitted by the promoter has been scrutinized by the concerned official, but the deficiency notice has not been dispatched till date. Therefore, in view of the same the matter is adjourned, and the concerned official is directed to dispatch the notice. The next date of hearing will be conveyed after submission of reply of deficiencies. EXAMINATION BY AUTHORITY View Order