Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
Ompee Tower Gurugram, Haryana GURUGRAM Gurgaon Ompee Construction
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/749/481/2023/93 DATED 16.10.2023 RERA-GRG-1435-2023 25-Aug-2023 25-Aug-2023 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 06-Sep-2023 BY HAND AND THROUGH MAIL BY HAND AND THROUGH MAIL
First hearing fixed View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/749/481/2023/93 DATED 16.10.2023 06-Jun-2024 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
16-Oct-2023 Sh. Ashish Kush, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Yogender Hooda, Partner of the company is present on behalf of the promoter. Approved subject to submission of signed copy of zoning plan and an undertaking to abide by condition of HSIIDC pertaining to allotment of the site and the same will also be incorporated in the Registration Certificate. The promoter shall submit the BG/DD amounting to Rs 25 lakhs as a security amount to submit the Fire Scheme approval within 3 months The registration certificate shall be issued after the submission of above. APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
11-Sep-2023 Sh. Ashish Kush, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case. No reply has been submitted by the promoter company till 06.09.2023 against the deficiencies conveyed by the authority through notice dated 06.09.2023. Therefore, in view of the same the matter is adjourned, and the next date of hearing will be conveyed after submission of reply of deficiencies already conveyed. Further, if no response is received from the promoter within next 4 week’s time, in that case the concerned official to put up the matter on file for issuance of show cause notice as to why their application for registration of project may not be rejected following the due procedure under the Act of 2016. EXAMINATION BY AUTHORITY View Order