16-Oct-2023 |
Sh. Ashish Kush, Planning
Executive and Ms. Asha, Chartered Accountant briefed about the facts of the
case.
Sh. Yogender Hooda, Partner
of the company is present on behalf of the promoter.
Approved subject to
submission of signed copy of zoning plan and an undertaking to abide by
condition of HSIIDC pertaining to allotment of the site and the same will also
be incorporated in the Registration Certificate. The promoter shall submit the
BG/DD amounting to Rs 25 lakhs as a security amount to submit the Fire Scheme approval within 3 months The registration
certificate shall be issued after the submission of above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
11-Sep-2023 |
Sh. Ashish Kush, Planning
Executive and Ms. Asha, Chartered Accountant briefed about the facts of the
case.
No
reply has been submitted by the promoter company till 06.09.2023 against the
deficiencies conveyed by the authority through notice dated 06.09.2023. Therefore,
in view of the same the matter is adjourned, and the next date of hearing will
be conveyed after submission of reply of deficiencies already conveyed.
Further,
if no response is received from the promoter within next 4 week’s time, in that
case the concerned official to put up the matter on file for issuance of show
cause notice as to why their application for registration of project may not be
rejected following the due procedure under the Act of 2016. |
EXAMINATION BY AUTHORITY |
View Order |