Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
Vedattam Revenue Estate of Village Gurugram, Sector-14, Gurugram, Haryana GURUGRAM Gurgaon SPJ PROPERTIES PRIVATE LIMITED
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/775/507/2024/02 DATED 08.01.2024 RERA-GRG-1419-2023 08-Aug-2023 07-Aug-2023 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 21-Aug-2023 Online 1st deficiency notice
First hearing View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/775/507/2024/02 DATED 08.01.2024 13-Feb-2024 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
08-Jan-2024 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Hitesh Garg (AR), Sh. Himanshu Gupta (AR) and Sh. Akash Gupta (AR) are present on behalf of the promoter. Approved as proposed.  APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
20-Nov-2023 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. No reply has been submitted by the promoter company against the deficiencies conveyed by the authority during last hearing dated 16.10.2023. Therefore, in view of the same the matter is adjourned, and the next date of hearing will be conveyed after submission of reply of deficiencies already conveyed. Further, if no response is received from the promoter within next 4 week’s time, in that case the concerned official to put up the matter on file for issuance of show cause notice as to why their application for registration of project may not be rejected following the due procedure under the Act of 2016. ADJOURNMENT View Order
16-Oct-2023 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Himanshu Gupta, Counsel is present on behalf of the promoter and seeks leave of absence on behalf of the promoter who has to go out of station due to some death in the family and further states that the approval of standard design is under consideration of DGTCP and seeks three weeks time for submission of approved standard design along with rectification of other deficit documents. The matter to come up on 20.11.2023.  ADJOURNMENT View Order
28-Aug-2023 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. No reply has been submitted by the promoter company against the deficiencies raised by the authority till 24.08.2023. In view of the same the matter is adjourned, and the next date of hearing will be conveyed after the submission of reply of deficiencies already conveyed through notice. EXAMINATION BY AUTHORITY View Order