Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
METRO WORLD MALL Multiplex Site, Sector 55-56, District Centre, Gurugram - 122011, Haryana GURUGRAM Wazirabad ST CORAL REALTORS PRIVATE LIMITED
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/968/700/2025/71 DATED 10.07.2025 RERA-GRG-1403-2023 28-Jun-2023 27-Jun-2023 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 11-Jul-2023 Online and By hand 1st deficiency notice
First hearing View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/968/700/2025/71 DATED 10.07.2025 29-Jul-2025 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
26-Feb-2024 Sh. Sumeet, Engineering Officer and Sh. Ashish, Chartered Accountant briefed about the facts of the case. Sh. V.K. Jain (AR), Sh. Ravi Kashyap (AR) and Sh. Ankur Jain (AR) are present on behalf of the promoter. The AR states that part OC in respect of the building constructed stand obtained in December 2019 and the OC for remaining portion already stand applied after completing the construction as per revised sanctioned plan. The requisite consent of 2/3rd allottees already stand obtained and submitted in the authority and the compliance of revalidation of building plans, the requisite revalidation fee stand deposited in HSVP office along with application for OC and grant of OC is expected shortly and project will be complete in all respect by December 2024. In view of the above, the Authority decides to grant registration to the project. The grant of registration is without prejudice to the rights of the allottees under section 14 who have not consented to the proposed revisions/changes. Further the promoter has applied for registration after creation of 3rd party rights and separate suo-motu proceedings initiated by the Authority are being clubbed with the above case and the Authority decides to impose a penalty of Rs. 50 lakhs. The registration certificate will be issued after receipt of the penalty.  APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
12-Feb-2024 Sh. Sumeet, Engineering Officer and Sh. Ashish, Chartered Accountant briefed about the facts of the case. Sh. V.K Jain (Director), Sh. Ankur Jain and Sh. Ravi Kashyap are present on behalf of the promoter. The AR of the promoter company states that they obtained the part occupation certificate for the project on 26.12.2019 and submitted the application for occupation certificate of balance area on 15.12.2023. Further, the AR of the promoter states that the building plans of the project will also be revalidated simultaneously for which they have submitted the requisite fee and will comply with the directions of the competent authority if any for the approval. The authority observes that penal proceedings regarding non-registration of project are also pending. Therefore, the case to be heard along with the Suo moto non-registration case on 26.02.2024. ADJOURNMENT View Order
18-Dec-2023 Sh. Sumeet, Engineering Officer and Ms. Asha Chartered Accountant briefed about the facts of the case. Sh. Hirdesh Kumar Sahu (AR) and Sh. Ravi Kashyap (AR) are present on behalf of the promoter. The AR of the promoter seeks eight weeks time to deposit the deficit fee and to comply with the remaining deficiencies pointed out on the grounds that the director of the promoter has gone under open heart surgery on 06.12.2023. In view of the above, final opportunity of eight weeks is granted to comply with the deficiencies subject to the directions that no further 3rd party rights shall be created in the project and an advertisement to this effect shall be published in the newspapers of local circulation. The matter to come up on 12.02.2024. ADJOURNMENT View Order
20-Nov-2023 Sh. Sumeet, Engineering Officer and Ms. Asha Chartered Accountant briefed about the facts of the case. Sh. VK Jain (Director) and Sh. Ravi Kashyap (AR) are present on behalf of the promoter. The AR of the promoter states that they have submitted the reply to the deficiencies in the authority on 17.11.2023 and further seeks four weeks’ time to submit the remaining requisite information/deficiencies. In view of the same the matter is adjourned and meanwhile the office to examine the reply submitted by the promoter. The matter to come up on 18.12.2023 for further proceedings. ADJOURNMENT View Order
16-Oct-2023 Sh. Sumeet, Engineering Officer and Ms. Asha Chartered Accountant briefed about the facts of the case. Sh. Nishant Yadav (Advocate) and Sh. Ravi Kashyap are present on behalf of the promoter. The Counsel in the absence of AR for promoter seeks three weeks time to comply with the deficiencies. One month time is given as a last opportunity to comply with the deficiencies failing which the application for registration shall be rejected and consequent action under the Act of 2016 and rules thereunder shall follow. The matter to come up on 20.11.2023.  ADJOURNMENT View Order
28-Aug-2023 Sh. Sumeet, Engineering Officer and Ms. Asha Chartered Accountant briefed about the facts of the case. No reply has been submitted by the promoter company against the deficiencies raised by the authority till 24.08.2023. In view of the same the matter is adjourned, and the next date of hearing will be conveyed after the submission of reply of deficiencies already conveyed through notice and last hearing dated 17.07.2023. ADJOURNMENT View Order
17-Jul-2023 Sh. Sumeet, Engineering Officer and Ms. Asha Chartered Accountant briefed about the facts of the case. Sh. Nishant Yadav (Advocate) and Sh. Hirdesh Kumar Sahu (AR) are present on behalf of the promoter. The AR of the promoter requests for six weeks’ time to attend the deficiencies failing which penal proceedings shall be initiated against the promoter. The matter to come up on 28.08.2023. EXAMINATION BY AUTHORITY View Order