Comprehensive Project Details (Project Extension)
Project Location Details (Project Extension)
Project Name Project Location Project District Project Tehsil Promoter Name
Commercial project Sector-102, dhankot, gurugram GURUGRAM JMS BUildtech pvt. ltd
Project Detail
Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks
RERA-GRG-1398-2023 22-Jun-2023 22-Jun-2023 EXTENSION APPROVED NOT REQUIRED Yes 28-Jun-2023 online 1st deficiency notice
First hearing
Project Listing Details (Project Extension)
Date of Hearing Proceedings of the day Status Order
24-Jun-2024 Sh. Ashish Kush, Planning Executive and Sh. Ashish, Chartered Accountant briefed about the facts of the project. Pushpender Singh (AR), Sh. Vipul Kumar Dahiya (AR) and Sh. Rishabh Jain (AR) are present on behalf of the promoter. Approved as proposed. The Registration Certificate shall be issued after submission of above documents. EXTENSION APPROVED View Order
27-May-2024 Sh. Sumeet, Engineering Officer and Sh. Ashish, Chartered Accountant briefed about the facts of the project. Sh. Vipul Kumar (AR) and Sh. Rishabh Jain (Advocate) are present on behalf of the promoter. The AR of the promoter states that the building plans of the project have been revised and submitted the variations in the building plans in tabular form and superimposed floor plans.  The AR of the promoter further states that the sale has been made based on revised buildings plans after obtaining necessary consents from the allottees. Therefore, the promoter is directed to submit the consent of 2/3rd unique allottees. Further after submission of consents of the allottees, a public notice shall also be issued in two prominent newspapers one Hindi and one English regarding the revision in building plans and submission of consents against the same for inviting objections if any within 10 days of publication. Further, at the time of revision in building plans, the promoter has availed the additional FAR 12% in lieu of GRIHA rating. Therefore, the promoter is hereby directed to submit the deficit fees as per revised building plans. The matter to come up on 24.06.2024. ADJOURNMENT View Order
13-May-2024 Sh. Sumeet, Engineering Officer and Sh. Ashish, Chartered Accountant briefed about the facts of the project. Sh. Pushpender Singh (AR), Sh. Vipul Dahiya (AR) and Sh. Rishabh Jain (Advocate) are present on behalf of the promoter. The promoter is directed to submit the table of changes in the revised building plan vis a vis the original building plans duly marked on the plans along with other deficiencies. The matter to come up on 27.05.2024. ADJOURNMENT View Order
22-Apr-2024 Sh. Sumeet, Engineering Officer and Sh. Ashish, Chartered Accountant briefed about the facts of the project. Sh. Vipul Dahiya (AR) and Sh. Rishabh Jain (Advocate) are present on behalf of the promoter. The reply has been submitted by the promoter on 19.04.2024. The concerned official to examine the same. The director/CEO/Project-Incharge of the promoter company is directed to be present along with the landowner on the next date of hearing. The matter to come up on 13.05.2024. ADJOURNMENT View Order
04-Mar-2024 Sh. Sumeet, Engineering Officer briefed about the facts of the project. Sh. Vipul Dahiya (AR) along with Sh. Rishabh Jain (Advocate) are present on behalf of the promoter. The promoter applied for extension of registration of project on 07.06.2023 but the deficiencies conveyed by the authority are not removed till date. Further a show cause notice dated 13.10.2023 for rejection of extension application already stand issued and no reply has been submitted by the promoter against the same. The authority decided that the matter to be submitted on file by the concerned official before the authority for taking further decision in this matter. ADJOURNMENT View Order
20-Nov-2023 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. No reply has been submitted by the promoter company against the deficiencies conveyed by the authority during last hearing dated 09.10.2023 till 15.11.2023. Therefore, in view of the same the matter is adjourned, and the next date of hearing will be conveyed after submission of reply of deficiencies already conveyed. Further, if no response is received from the promoter within next 4 week’s time, in that case the concerned official to put up the matter on file for issuance of show cause notice as to why their application for registration of project may not be rejected following the due procedure under the Act of 2016. ADJOURNMENT View Order
09-Oct-2023 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Rishabh Jain (Advocate) and Sh. Vipul Kumar Dahiya (AR) are present on behalf of the promoter. It is noted by the Authority that even the basic compliances like fire scheme approval and approval of service plans and estimates have not been obtained by the promoter even at this belated stage. The promoter has also failed to submit all the QPRs and 4(2)(l)(D) reports. In view of the above, a show cause notice be issued to the promoter as to why the application for extension under section 6 of the Act may not be rejected and further proceedings invoked against the project. The matter to come up on 20.11.2023. ADJOURNMENT View Order
07-Aug-2023 As per the directions of the authority, the matter is fixed for hearing on 09.10.2023. ADJOURNMENT View Order
03-Jul-2023 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Rishabh Jain (Advocate) is present on behalf of the promoter and requests for 4 weeks adjournment to file the reply and deficit documents. Request is allowed.  The matter to come up on 07.08.2023. EXAMINATION BY AUTHORITY View Order