24-Jul-2023 |
Sh. Shashank Sharma, Associate
Engineer Executive briefed about the facts of the project.
Sh. Dheeraj Yadav (AR) is present on behalf of the promoter.
It is noted that DTCP has freezed the Pocket-2
comprising the tower A, B, G and commercial as shown in the approved site plan until
the 66KV line will be shifted by the promoter.
The Authority hereby decides to approve
as proposed subject to a condition that no third-party rights shall be created
on the area frozen by DTCP i.e., Pocket-2 comprising the tower A, B, G and
commercial as shown in the approved site plan on account of shifting of power
line without obtaining the order of defreeze from DTCP and intimation of the
same to the Authority. The RC shall be
issued only after the corrections done in online DPI and A-H form. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
03-Jul-2023 |
Proceedings dated 03.07.2023
Sh. Shashank Sharma, Associate
Engineer Executive briefed about the facts of the project.
None is present on behalf of the
promoter. An e-mail has been received from the applicant promoter requesting
for adjournment of the hearing to 10.07.2023 instead of 03.07.2023. However, it
is noticed that even the approval of building plans has not been yet obtained
which is a pre-requisite for making application for registration. In view of the above, show cause notice for
reply within one month may be issued as to why the application for registration
may not be rejected. It is also noticed that one complaint dated 01.06.2023 has
been received against the applicant and a reply to the same was sought from the
applicant promoter which has been received on 15.06.2023. The complainant may
also be called to be present on the next date of hearing.
The matter to come up on
07.08.2023. |
ADJOURNMENT |
View Order |
19-Jun-2023 |
Sh. Shashank Sharma, Associate
Engineer Executive briefed about the facts of the project.
Sh. Dheeraj Yadav (AR), Sh. Heera
Bisht (AR) and Sh. Dheeraj Sood (AR) are present on behalf of the promoter.
The promoter has submitted reply to
the complaint dated 07.06.2023 and seeks a short adjournment for submission of
approved building plans.
The matter to come up on 03.07.2023. |
ADJOURNMENT |
View Order |
12-Jun-2023 |
Sh. Shashank Sharma, Associate
Engineer Executive briefed about the facts of the project.
Sh. Dheeraj Yadav(AR), sh. Dheeraj
Sood (AR) and Sh. Heera Bisht (AR) are present on behalf of the promoter.
The AR of the promoter requested for
one week time to rectify deficiencies.
The matter to come up on 19.06.2023. |
EXAMINATION BY AUTHORITY |
View Order |