Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
YASHIKA GREEN SQUARE Sector-99A, Village Gopalpur, Gururgam GURUGRAM Gurgaon Dishita Infra Pvt. Ltd.
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/737/469/2023/81 DATED 24.07.2023 RERA-GRG-1386-2023 19-May-2023 14-May-2023 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 31-May-2023 By Hand By Hand
First hearing fixed View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/737/469/2023/81 DATED 24.07.2023 14-Nov-2023 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
24-Jul-2023 Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. Sh. Dheeraj Yadav (AR) is present on behalf of the promoter. It is noted that DTCP has freezed the Pocket-2 comprising the tower A, B, G and commercial as shown in the approved site plan until the 66KV line will be shifted by the promoter. The Authority hereby decides to approve as proposed subject to a condition that no third-party rights shall be created on the area frozen by DTCP i.e., Pocket-2 comprising the tower A, B, G and commercial as shown in the approved site plan on account of shifting of power line without obtaining the order of defreeze from DTCP and intimation of the same to the Authority. The RC shall be issued only after the corrections done in online DPI and A-H form. APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
03-Jul-2023 Proceedings dated 03.07.2023 Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. None is present on behalf of the promoter. An e-mail has been received from the applicant promoter requesting for adjournment of the hearing to 10.07.2023 instead of 03.07.2023. However, it is noticed that even the approval of building plans has not been yet obtained which is a pre-requisite for making application for registration.  In view of the above, show cause notice for reply within one month may be issued as to why the application for registration may not be rejected. It is also noticed that one complaint dated 01.06.2023 has been received against the applicant and a reply to the same was sought from the applicant promoter which has been received on 15.06.2023. The complainant may also be called to be present on the next date of hearing. The matter to come up on 07.08.2023.   ADJOURNMENT View Order
19-Jun-2023 Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. Sh. Dheeraj Yadav (AR), Sh. Heera Bisht (AR) and Sh. Dheeraj Sood (AR) are present on behalf of the promoter. The promoter has submitted reply to the complaint dated 07.06.2023 and seeks a short adjournment for submission of approved building plans. The matter to come up on 03.07.2023. ADJOURNMENT View Order
12-Jun-2023 Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. Sh. Dheeraj Yadav(AR), sh. Dheeraj Sood (AR) and Sh. Heera Bisht (AR) are present on behalf of the promoter. The AR of the promoter requested for one week time to rectify deficiencies. The matter to come up on 19.06.2023. EXAMINATION BY AUTHORITY View Order