| 29-Jan-2024 |
Sh. Shashank Sharma, Associate Engineer
Executive and Sh. Ashish Dubey briefed about the facts of the project.
Sh. Anurag Srivastava (GM) and Sh. Naveen
Kumar (Arch.) are present on behalf of the promoter.
The AR states that BG/DD of Rs. 25 lakh in
lieu of approval of revised service plans and estimates has been submitted in
the Authority and shall be submitting clarificatory letter from the concerned
bank regarding creation of 3rd party rights.
Approved as proposed above and subject to
submission of letter from bank. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
| 22-Jan-2024 |
Sh. Shashank Sharma, Associate Engineer
Executive and Sh. M.L Sardana briefed about the facts of the project.
Sh. Anurag Srivastava (GM), Sh. Vedant Batra
(CS) and Sh. Ravinder (AR) are present on behalf of the promoter.
The AR states that revised approval of fire
scheme has been obtained and submitted along with other deficit documents
except for revised approval of service plans estimates and non-encumbrance
certificate. The service plans estimate as per earlier approved schemes already
stands submitted and revision in lieu of increase in number of shops are in
process of approval and final approval shall be submitted in the Authority in
three months and a BG of Rs. 25 lakhs shall also be submitted along with a
clarification from the concerned financial institution for creation of 3rd
party rights in respect of the units under consideration for registration.
The matter to come up on 29.01.2024. |
ADJOURNMENT |
View Order |
| 01-Jan-2024 |
Sh. Shashank Sharma, Associate Engineer
Executive briefed about the facts of the project.
Sh. Ravinder (AR) is present on behalf of the
promoter.
The AR states that the deficit documents along
with the fee has been submitted on 29.12.2023. Further since there are
variations/changes vis a vis earlier approved layout plan of
licensed/registered project and hence a public notice for objection if any be
also issued by office within two days. Further the promoter has availed loan
against the project land and hence clearance of bank for undertaking sale of
the units be also submitted.
The matter to come up on 22.01.2024. |
ADJOURNMENT |
View Order |
| 18-Dec-2023 |
Sh. Shashank Sharma, Associate Engineer
Executive briefed about the facts of the project.
Sh. Anurag Srivastava (General Manager), Sh.
Vedant Batra (AR) and Sh. Ravinder (AR) are present on behalf of the promoter.
The AR of the promoter requests for one week
adjournment to deposit the deficit fee and remove the remaining deficiencies.
The matter to come up on 01.01.2024. |
ADJOURNMENT |
View Order |
| 30-Oct-2023 |
Sh. Shashank Sharma, Associate Engineer
Executive briefed about the facts of the project.
The application submitted by the promoter has been
scrutinized by the concerned official, but the deficiency notice has not been
dispatched till date. In view of the same the matter is adjourned, and the next
date of hearing will be conveyed only after the submission of replies to the
deficiencies conveyed through deficiency notice. Further, if no response is
received from the promoter within next 4 weeks' time, in that case the
concerned official to put up the matter on file for issuance of show cause notice
as to why their application for registration of project may not be rejected
following the due procedure under the Act of 2016. |