| 07-Aug-2023 |
Sh. Sumeet, Engineering
Officer and Ms. Asha, Chartered Accountant briefed about the facts of the
project.
Sh.
Vedant Batra (CS) and Sh. Ravinder (AR) are present on behalf of the promoter.
Approved as proposed. The
certificate be issued after compliance mentioned as above. |
EXTENSION APPROVED |
View Order |
| 17-Jul-2023 |
Sh. Sumeet, Engineering
Officer and Ms. Asha, Chartered Accountant briefed about the facts of the
project.
Sh. Vedant Batra (CS) and
Sh. Mintu Kumar (AR) are present on behalf of the promoter. The AR of the
promoter requests for two weeks’ adjournment. The same is allowed.
The matter to come up on
07.08.2023. |
ADJOURNMENT |
View Order |
| 03-Jul-2023 |
Sh. Sumeet, Engineering
Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project.
Sh. Vedant Batra(AR) is
present on behalf of the promoter and seeks two weeks adjournment.
The matter to come up on
17.07.2023. |
ADJOURNMENT |
View Order |
| 19-Jun-2023 |
Sh. Sumeet, Engineering
Officer and Ms. Asha, Chartered Accountant briefed about the facts of the
project.
Sh. Anurag Srivastava
(Manager) and Sh. Vedant Batra (AR) are
present on behalf of the promoter.
The reply submitted on
15.06.2023 which needs to be examined by the authority.
The matter to come up on
03.07.2023. |
ADJOURNMENT |
View Order |
| 29-May-2023 |
Proceedings dated: 29.05.2023.
Sh. Sumeet, Engineering
Officer and Ms. Asha, Chartered Accountant briefed about the facts of the
project.
Sh.Vedant Batra, Company Secretary, is present on the behalf of the promoter.
The AR of the promoter has requested for two weeks’
time to submit reply to the deficiencies conveyed in the notice.
The matter to come up on 19.6.2023. |
EXAMINATION BY AUTHORITY |
View Order |