Comprehensive Project Details (Project Extension)
Project Location Details (Project Extension)
Project Name Project Location Project District Project Tehsil Promoter Name
Signature Global SCOII 88A Village-Harsaru, Sector-88A, Gurugram GURUGRAM JMK Holdings Pvt. Ltd.
Project Detail
Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks
RERA-GRG-1381-2023 05-May-2023 05-May-2023 EXTENSION APPROVED NOT REQUIRED Yes 24-May-2023 Online 1st deficiency notice
First hearing
Project Listing Details (Project Extension)
Date of Hearing Proceedings of the day Status Order
07-Aug-2023 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Vedant Batra (CS) and Sh. Ravinder (AR) are present on behalf of the promoter. Approved as proposed. The certificate be issued after compliance mentioned  as above.  EXTENSION APPROVED View Order
17-Jul-2023 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Vedant Batra (CS) and Sh. Mintu Kumar (AR) are present on behalf of the promoter. The AR of the promoter requests for two weeks’ adjournment. The same is allowed. The matter to come up on 07.08.2023. ADJOURNMENT View Order
03-Jul-2023 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Vedant Batra(AR) is present on behalf of the promoter and seeks two weeks adjournment. The matter to come up on 17.07.2023.  ADJOURNMENT View Order
19-Jun-2023 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Anurag Srivastava (Manager) and Sh. Vedant Batra  (AR) are present on behalf of the promoter. The reply submitted on 15.06.2023 which needs to be examined by the authority. The matter to come up on 03.07.2023. ADJOURNMENT View Order
29-May-2023 Proceedings dated: 29.05.2023. Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh.Vedant Batra, Company Secretary,   is present on the behalf of the promoter. The AR of the promoter has requested for two weeks’ time to submit reply to the deficiencies conveyed in the notice. The matter to come up on 19.6.2023. EXAMINATION BY AUTHORITY View Order