| 07-Aug-2023 |
Sh. Sumeet, Engineering
Officer and Ms. Asha, Chartered Accountant briefed about the facts of the
project.
Sh.
Vedant Batra (CS) and Sh. Ravinder (AR) are present on behalf of the promoter.
The AR of
the promoter verifies that only one plot has been sold till date under the
above scheme and earlier only a provisional allotment letter was issued on
receipt of payment less than 10% of the earnest money. Subsequently, allotment
letter has been issued as per prescribed format and an undertaking for not
allotting any plot except above one plot has been submitted
Along with copy of the
allotment letter issued to one allottee. The remaining compliances including
approval of competent authority are submitted and the applicant is seeking
extension of one year from the expiry of the registration period. In view of
the above the request is allowed. |
EXTENSION APPROVED |
View Order |
| 17-Jul-2023 |
Sh. Sumeet, Engineering
Officer and Ms. Asha, Chartered Accountant briefed about the facts of the
project.
Sh. Vedant Batra (CS) and
Sh. Mintu Kumar (AR) are present on behalf of the promoter. The AR of the
promoter requests for two weeks’ adjournment. The same is allowed.
The matter to come up on
07.08.2023. |
ADJOURNMENT |
View Order |
| 03-Jul-2023 |
Sh. Sumeet, Engineering
Officer and Ms. Asha, Chartered Accountant briefed about the facts of the
project.
Sh. Vedant Batra(AR) is
present on behalf of the promoter and seeks two weeks adjournment.
The matter to come up on
17.07.2023. |
ADJOURNMENT |
View Order |
| 19-Jun-2023 |
Sh. Sumeet, Engineering
Officer and Ms. Asha, Chartered Accountant briefed about the facts of the
project.
Sh. Anurag Srivastava
(Manager) and Sh. Vedant Batra (AR) are present on behalf of the promoter.
The reply submitted on
15.06.2023 which needs to be examined by the authority.
The matter to come up on
03.07.2023. |
ADJOURNMENT |
View Order |
| 29-May-2023 |
Proceedings dated: 29.05.2023.
Sh. Sumeet, Engineering
Officer and Ms. Asha, Chartered Accountant briefed about the facts of the
project.
Sh.Vedant Batra, Company Secretary, is present on the behalf of the promoter.
The AR of the promoter has requested for two weeks’
time to submit reply to the deficiencies conveyed in the notice.
The matter to come up on 19.6.2023 |
EXAMINATION BY AUTHORITY |
View Order |