Comprehensive Project Details (Project Extension)
Project Location Details (Project Extension)
Project Name Project Location Project District Project Tehsil Promoter Name
SAAN VERDANTE SECTOR-95 GURUGRAM SAAN Procon Pvt. Ltd.
Project Detail
Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks
RERA-GRG-1379-2023 05-May-2023 05-May-2023 EXTENSION APPROVED NOT REQUIRED Yes 23-May-2023 HARERA/GGM/ERPIN/59 DISPATCHED
First hearing
Project Listing Details (Project Extension)
Date of Hearing Proceedings of the day Status Order
26-Jun-2023 Ms. Prachi Singh, Planning Executive briefed about the facts of the case. Sh. Rajan Bajaj (Director) is present on behalf of the promoter. Approved as proposed subject to submission of corrected copy REP-V and DPI. The extension is granted only for one year i.e., 29.05.2024 for which the promoter has submitted revised REP-II and 4(2)(l)(D) affidavit.  EXTENSION APPROVED View Order
19-Jun-2023 Ms. Prachi Singh, Planning Executive briefed about the facts of the case. Sh. Venket Rao (Advocate), Ms. Ankita Saikia (Advocate), and Sh. Pankaj Chandola (Advocate) are present on the behalf of the promoter. The promoter Director present undertakes to submit copy of the original license, building plans, service plans estimates and fire scheme for the project and remove rest of the deficiencies  within a period of three days. The matter to come up on 26.06.2023.  OBJECTION View Order
29-May-2023 Proceedings dated: 29.05.2023 Ms. Prachi Singh, Planning Executive briefed about the facts of the case. Shri Venket Rao and Sh. Vikas, authorized representative are present on behalf of the promoter and request three weeks’ time to clear the deficiencies. The matter to come up on 19.6.2023 for further proceedings.  EXAMINATION BY AUTHORITY View Order
Project Deficiency Details
Deficiency Date Deficiency Remarks Online Compliance Done Online Compliance Date Online Compliance Remarks Compliance Date Compliance Remarks
01-Jun-2023 Proceedings dated: 29.05.2023 Ms. Prachi Singh, Planning Executive briefed about the facts of the case. Shri Venket Rao and Sh. Vikas, authorized representative are present on behalf of the promoter and request three weeks’ time to clear the deficiencies. The matter to come up on 19.6.2023 for further proceedings.  Not Yet