| 28-Aug-2023 |
Ar. Neeraj Gautam, Associate Architectural Executive
and Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Manoj Kapoor, Sh. Rajnish Mishra (AR), Sh. Vijay
Kumar and Ms. Sangeeta Jain are present on the behalf of the promoter.The AR submits that the project is already complete up
to 90% and is expected to be completed by December 2023. Further, the AR is
reconciling the errors in DPI and is submitting revised bank undertaking
clarifying the Account Number as per prescribed format.
The Authority decides to approve the extension of
registration of the project as proposed. The certificate of extension shall be
issued after the promoter has submitted the above corrected documents as well
as corrected DPI in the Authority. |
EXTENSION APPROVED |
View Order |
| 07-Aug-2023 |
Ar. Neeraj Gautam, Associate Architectural Executive
and Ms. Asha, Chartered Accountant briefed about the facts of the case.
Sh. Rajanish Mishra (Adv.), Sh. Vijay Kumar and Ms.
Sangeeta Jain are present on the behalf of the promoter.
Reply submitted by the promoter on 04.08.2023. Office
to examine the details.
The matter to come up for further discussions on
28.08.2023. |
ADJOURNMENT |
View Order |
| 31-Jul-2023 |
Due to Govt. Holiday, the matter is adjourned to 07.08.2023. |
ADJOURNMENT |
--- |
| 10-Jul-2023 |
Ar. Neeraj Gautam, Associate Architectural Executive
and Ms. Asha, Chartered Accountant briefed about the facts of the case.
Sh. Manoj Kapoor, Sh. Rajanish Mishra (AR) and Ms.
Sangeeta Jain are present on the behalf of the promoter.
The AR of the promoter has submitted a reply in the
Authority today which needs to be scrutinized by the concerned executive. The
AR of the promoter requests three weeks’ time to submit the updated DPI and
deficit fee in the Authority.
The matter to come up on 31.07.2023 |
ADJOURNMENT |
--- |
| 07-Jun-2023 |
Ar. Neeraj Gautam, Associate Architectural Executive
and Ms. Asha, Chartered Accountant briefed about the facts of the case.
Sh. Rajnish Mishra (AR) and Ms. Sangeeta Jain are present on the
behalf of the promoter.
The AR of the company requests for one month time for
complying with the deficiencies.
The matter to come up on 10.07.2023. |
ADJOURNMENT |
View Order |
| 05-Jun-2023 |
Coram is not complete. The matter is placed
before the authority and as per the directions of authority the matter is
adjourned to 07.06.2023. |
ADJOURNMENT |
--- |
| 08-May-2023 |
Ar. Neeraj Gautam, Associate Architectural Executive
and Ms. Asha, Chartered Accountant briefed about the facts of the case.
Sh. Manoj Kapoor (Principal Consultant), Sh. Vijay
Kumar (MD) and Sh. Rajanish Mishra (AR) are present on the behalf of the
promoter.
The AR of the promoter states that the reply is being
submitted in the Authority today. The office to examine and submit before the
next date of hearing.
The matter to come up on 05.06.2023. |
EXAMINATION BY AUTHORITY |
View Order |