| 11-Dec-2023 |
Sh.
Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about
the facts of the project.
Sh.
Avinash Sharma (AR) is present on behalf of the promoter.
The
AR of the promoter states that construction of tower had been completed
including other development works and OC had already been applied to DGTCP
which is in advance stage of approval.
In
view of the same approved as proposed. |
EXTENSION APPROVED |
View Order |
| 04-Dec-2023 |
Sh.
Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about
the facts of the project.
Sh. Avinash Sharma (AR) is present on behalf of the promoter.
The
AR of the promoter states that reply to the deficiencies has been submitted on 30.11.2023
and 04.12.2023. Further the AR states that the QPR’s are not being uploaded due
to technical fault of the website. The promoter is directed to resolve the
issue with the IT team of the authority and submit the pending QPR’s and annual
audit report under section 4(2)(l)(D) of the Act of 2016. Meanwhile, the reply
submitted by the promoter be got examined.
The
matter to come up on 18.12.2023. |
ADJOURNMENT |
View Order |
| 20-Nov-2023 |
Sh. Sumeet, Engineering
Officer and Ms. Asha, Chartered Accountant briefed about the facts of the
project.
Sh. Avinash Sharma (AR) is present on behalf
of the promoter.
The AR of the promoter
states that all the units have been sold out and no further sale is to be made.
However, they will submit the draft prescribed format for BBA to be executed
with the allottees. The promoter is directed to submit the copies of 10 BBA’s
executed with the allottees along with other deficit documents. Further, the
promoter is also directed to submit the pending QPR and 4(2)(l)(D) reports.
The AR of the promoter
submits that they have applied for an occupation certificate and the same is
expected in the next two months.
Matter to come up on 04.12.2023
for further proceedings. |
ADJOURNMENT |
View Order |
| 23-Oct-2023 |
Sh.
Sumeet, Engineering Officer briefed about the facts of the project.
Sh.
Avinash Sharma (AR) is present on behalf of the promoter.
The
AR of the promoter states that they are submitting the reply today itself and
further requests to grant two weeks’ time for submission of renewed license,
approved service plan & estimates and other deficit documents. Therefore,
the matter is adjourned and to come up on 20.11.2023. |
ADJOURNMENT |
View Order |
| 18-Sep-2023 |
Sh.
Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about
the facts of the project.
None
is present on behalf of the promoter. As per the record eight opportunities
have been provided to the promoter to rectify the deficiencies but the
deficiencies have not been removed till date. However, as on date the license
of the project also stand expired on 17.09.2023 which also needs to be get
renewed by the promoter including the approval of service plan and estimates
for the project. Further, the revised deficit fee amounting Rs. 78,693 for incorporating
the additional 3% FAR granted by DTCP on account of solid waste management also
needs to be deposited.
A
show cause notice for rejection of application for extension of registration of
project be issued to the promoter as per the Act of 2016.
The
matter is adjourned and to come up on 23.10.2023. |
ADJOURNMENT |
View Order |
| 28-Aug-2023 |
Sh.
Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about
the facts of the project.
Sh.
Avinash Sharma (AR) is present on behalf of the promoter.
The
AR submits that the revision of plan was only on account of 3% extra FAR taken
on account of solid waste management. Further the consent of more than 2/3rd
allottees for the above revision has already been obtained and submitted in the
Authority including issuance of public notice on behalf of the Authority for
filing of objections if any. The concerned Engineering Executive confirms that
no objection in respect of the above public notice has been received. Further
regarding submission of approved service plans and estimates, the AR states
that the same are at advance stage in DTCP office and requests for its
submission in two weeks. One more opportunity for submission of approved
service plans and estimates is granted. Fees for extension of registration is
paid only in respect of the area already registered and hence the fees for
increased area on account of extra FAR for solid waste management be also
deposited for incorporating the additional area.
The
matter to come up on 18.09.2023. |
ADJOURNMENT |
View Order |
| 24-Jul-2023 |
Ms.
Asha, Chartered Accountant briefed about the facts of the project.
Sh. Sunil Rawat and Sh. Avinash Sharma (AR) are present on behalf of the
promoter.
The AR of the promoter requests for four weeks adjournment for
rectification of the deficiencies. The Authority decided to give a last
opportunity to the promoter for rectification of all deficiencies mentioned
above.
The matter to come up on 28.08.2023. |
ADJOURNMENT |
View Order |
| 10-Jul-2023 |
Sh.
Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about
the facts of the project.
Sh.
Sunil Rawat and Sh. Avinash Sharma are present on behalf of the promoter.
The
AR of the promoter stated that they have submitted the reply today itself which
needs to be examined by the office. Further, the AR of the promoter is directed
to submit the list of unique allottees duly authenticated in the project regarding
the consent submitted.
The
AR of the promoter is also directed to publish a public notice in the two
leading newspapers one Hindi and one English inviting objection within seven
days of publication, if any from the existing allottees regarding the revision
in the building plans.
The
matter to come up on 24.07.2023. |
ADJOURNMENT |
View Order |
| 03-Jul-2023 |
Sh.
Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about
the facts of the project.
Sh.
Avinash Sharma (AR) is present on behalf of the promoter.
The
promoter applicant has submitted reply today. The office may examine the same.
It is also observed that the building plan of the project has been revised and
there is increase in FAR by .03% on account of solid waste management facility.
The promoter is directed to submit if there are any changes in the earlier
approved building plans along with their details in tabular forms duly marked
on the plan in distinct colors. The NOC of 448 allottees out of 669 allottees
has been submitted and a list of unique allottees shall be submitted.
The
matter to come up on 10.07.2023. |
ADJOURNMENT |
View Order |
| 19-Jun-2023 |
Sh.
Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about
the facts of the project.
Sh.
Avinash Sharma (AR) is present on behalf of the promoter.
The
AR of the promoter seeks short adjournment.
The
matter to come up on 03.07.2023. |
ADJOURNMENT |
View Order |
| 29-May-2023 |
Proceedings
dated: 29.05.2023.
Sh.
Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about
the facts of the project.
Shri
Sunil Rawat, and Avinash Sharma, authorized representatives are present on
behalf of the promoter and seeks three weeks’ time to submit the requisite
information. Three weeks’ time is allowed to the promoter to submit the
requisite information to the authority.
Matter
to come up on 19.6.2023 for further proceedings. |
ADJOURNMENT |
View Order |
| 01-May-2023 |
Due to administrative work, the matter is adjourned to 29.05.2023. |
EXAMINATION BY AUTHORITY |
View Order |