Comprehensive Project Details (Project Extension)
Project Location Details (Project Extension)
Project Name Project Location Project District Project Tehsil Promoter Name
Signature Global SCO - 37D Village-Basai, Sector-37/D, Gurugram GURUGRAM Signature Global Developers Private limited
Project Detail
Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks
RERA-GRG-1351-2023 06-Apr-2023 06-Apr-2023 EXTENSION APPROVED NOT REQUIRED Yes 20-Apr-2023 By hand and Online 1st deficiency notice
First hearing fixed
Project Listing Details (Project Extension)
Date of Hearing Proceedings of the day Status Order
07-Aug-2023 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Vedant Batra (CS) and Sh. Ravinder (AR) are present on behalf of the promoter. Extension is granted. The penalty for delay submission of service plans and estimates is being dealt separately and will be levied accordingly.  EXTENSION APPROVED View Order
17-Jul-2023 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Vedant Batra (CS) and Sh. Mintu Kumar (AR) are present on behalf of the promoter. The AR of the promoter requests for two weeks’ adjournment. The same is allowed. The matter to come up on 07.08.2023. ADJOURNMENT View Order
03-Jul-2023 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Vedant Batra(AR) is present on behalf of the promoter and seeks two weeks adjournment. The matter to come up on 17.07.2023.  ADJOURNMENT View Order
26-Jun-2023 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Anurag Srivastava (GM) and Sh. Vedant Batra (CS) are present on behalf of the promoter. The AR of the promoter states that copy of allotment letter submitted in the Authority is a provisional one and they will submit a final allotment letter duly executed and accepted by the allottee and other deficient documents as mentioned above. The matter to come up on 03.07.2023. ADJOURNMENT View Order
07-Jun-2023 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Anurag Srivastava (GM) and Sh. Vedant Batra (CS) are present on behalf of the promoter. The promoter was required to submit BG amounting to Rs. 25 lakhs in lieu of submitting service plans and estimates within a period of three months in respect of the registration certificate No. 51 of 2022 dated 27.06.2022 but the same was not submitted. However, the service plans and estimates have been submitted having approval dated 02.11.2022 satisfying the above condition. This matter shall be taken up separately. Regarding rest of the compliances the AR submits that the reply has been submitted on 02.06.2023 which needs to be examined. The matter to come up on 26.06.2023.  ADJOURNMENT View Order
05-Jun-2023 Coram is not complete. The matter is placed before the authority and as per the directions of authority the matter is adjourned to 07.06.2023. ADJOURNMENT View Order
08-May-2023 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Anurag Srivastava (GM) and Sh. Vedant Batra (CS) are present on behalf of the promoter. The AR of the promoter stated that they have submitted the reply today itself. The office examines the same and the matter to come up on 05.06.2023. ADJOURNMENT View Order
24-Apr-2023 Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Vedant Batra (CS) and Sh. Ravinder (Executive) are present on behalf of the promoter. The AR requests for two weeks time for rectification of the deficiencies conveyed on 20.04.2023. Matter to come up on  08.05.2023. EXAMINATION BY AUTHORITY View Order