| 19-Jun-2023 |
Ms.
Prachi Singh, Planning Executive briefed about the facts of the project.
Sh. Anurag Srivastava
(Manager) and Sh. Vedant Batra (AR) are
present on behalf of the promoter.
Approved as proposed. |
EXTENSION APPROVED |
View Order |
| 07-Jun-2023 |
Ms. Prachi Singh,
Planning Executive briefed about the facts of the project.
Sh. Anurag Srivastava (GM)
and Sh. Vedant Batra (CS) are present on behalf of the
promoter.
The
reply has been submitted yesterday i.e. on 06.06.2023. The same may be
examined.
The
matter to come up on 19.06.2023. |
ADJOURNMENT |
View Order |
| 05-Jun-2023 |
Coram is not complete. The matter is placed
before the authority and as per the directions of authority the matter is
adjourned to 07.06.2023. |
ADJOURNMENT |
--- |
| 08-May-2023 |
Ms. Prachi Singh, Planning
Executive briefed about the facts of the case.
Sh. Anurag Srivastava is present on behalf of the promoter and
requests for three weeks time to comply with the deficiencies.
The mater to come up on
05.06.2023 |
ADJOURNMENT |
View Order |
| 24-Apr-2023 |
Ms.
Shashank Sharma, Associate Engineer Executive briefed about the facts of the
case.
Sh. Vedant Batra (CS) and
Sh. Ravinder (Executive) are present on behalf of the promoter.
The AR requests for two
weeks time for rectification of the deficiencies conveyed on 20.04.2023.
Matter to come up on 08.05.2023. |
EXAMINATION BY AUTHORITY |
View Order |