| 19-Jun-2023 |
Ar. Neeraj Gautam, Associate Architectural Executive
and Ms. Asha, Chartered Accountant briefed about the facts of the case.
Sh. Anurag Srivastava (Manager) Sh. Vedant Batra (AR)
are present on the behalf of the promoter.
Approved as proposed. |
EXTENSION APPROVED |
View Order |
| 29-May-2023 |
Proceedings dated 29.05.2023
Ar. Neeraj Gautam, Associate Architectural Executive and Ms. Asha,
Chartered Accountant briefed about the facts of the case. Sh.Vedant Batra, Company Secretary, is
present on the behalf of the promoter.
The promoter has requested to two week’ time to submit
reply to the remaining deficiencies.
Matter to come up on 19.06.2023.
|
ADJOURNMENT |
View Order |
| 15-May-2023 |
Ar. Neeraj Gautam, Associate Architectural Executive
and Ms. Asha, Chartered Accountant briefed about the facts of the case.
Sh. Vedant Batra (CS) is present on the behalf of the
promoter.
The AR of the promoter seeks an adjournment of two
weeks.
The matter to come up on 29.05.2023 |
ADJOURNMENT |
View Order |
| 01-May-2023 |
Due to administrative work, the matter is adjourned to 15.05.2023. |
ADJOURNMENT |
--- |
| 17-Apr-2023 |
Ar. Neeraj Gautam, Associate Architectural Executive
and Ms. Asha, Chartered Accountant briefed about the facts of the case.
Sh. Anurag Srivastava (GM) and Sh.
Vedant Batra (CS) are present on behalf of the promoter.
The AR of the promoter requested for two
weeks’ time for submission of the deficit documents.
The matter
to come up on 01.05.2023. |
EXAMINATION BY AUTHORITY |
View Order |