Comprehensive Project Details (Project Extension)
Project Location Details (Project Extension)
Project Name Project Location Project District Project Tehsil Promoter Name
PYRAMID FUSION HOMES VILLAGE PALRA SECTOR 70A GURUGRAM PYRAMID INFRATECH PRIVATE LIMITED
Project Detail
Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks
RERA-GRG-1320-2023 02-Mar-2023 02-Mar-2023 EXTENSION APPROVED NOT REQUIRED Yes 20-Mar-2023 By Hand By Hand
First hearing fixed
Project Listing Details (Project Extension)
Date of Hearing Proceedings of the day Status Order
08-May-2023 Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. Sh. Sunil (AR) is present on behalf of promoter. Approved as proposed for grant of one year extension u/s 6 for area already registered only subject to the submission of 4(2)(l)(d) report for the financial year 2019-20 and the promoter shall apply separately for registration of additional 12% FAR available under IGBC alongwith 2/3rd consents of the existing allottees. EXTENSION APPROVED View Order
24-Apr-2023 Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. Sh. Praveen Kumar Singh (AR), Sh. Sunil Kumar (AR) and Sh. Shrikant Kumar (AR) are present on behalf of the promoter. The AR of the promoter requests for two weeks time. The matter to come up on 08.05.2023. OBJECTION View Order
10-Apr-2023  Proceedings dated 10.04.2023 Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. Sh. Shrikant Kumar (Legal) and Sh. Praveen Kumar Singh (Accounts Finance) are present on behalf of the promoter. The AR of the promoter seeks two weeks’ time to comply with the deficiencies. The matter to come up on 24.04.2023. ADJOURNMENT View Order
20-Mar-2023 Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. None is present on behalf of the promoter. The matter to come up on 10.04.2023. EXAMINATION BY AUTHORITY View Order
Project Deficiency Details
Deficiency Date Deficiency Remarks Online Compliance Done Online Compliance Date Online Compliance Remarks Compliance Date Compliance Remarks
10-Apr-2023  Proceedings dated 10.04.2023 Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. Sh. Shrikant Kumar (Legal) and Sh. Praveen Kumar Singh (Accounts Finance) are present on behalf of the promoter. The AR of the promoter seeks two weeks’ time to comply with the deficiencies. The matter to come up on 24.04.2023. Not Yet