| 08-May-2023 |
Sh. Shashank Sharma, Associate Engineer
Executive briefed about the facts of the project.
Sh. Sunil (AR) is present on behalf of
promoter.
Approved as proposed subject to the
submission of 4(2)(l)(d) report for the financial year 2019-20. |
EXTENSION APPROVED |
View Order |
| 01-May-2023 |
Due to administrative work, the matter is adjourned to 08.05.2023. |
ADJOURNMENT |
View Order |
| 24-Apr-2023 |
Sh. Shashank Sharma, Associate
Engineer Executive briefed about the facts of the project.
Sh. Praveen Kumar Singh (AR), Sh. Sunil Kumar
(AR) and Sh. Shrikant Kumar (AR) are present on behalf of the promoter.
The AR of the promoter requests for one week
time.
The
matter to come up on 01.05.2023. |
OBJECTION |
View Order |
| 10-Apr-2023 |
Proceedings
dated 10.04.2023
Sh. Shashank Sharma, Associate Engineer
Executive briefed about the facts of the project.
Sh. Shrikant Kumar (Legal) and Sh.
Praveen Kumar Singh (Accounts Finance) are present on behalf of the promoter.
The AR submits that the reply has been
submitted today and CA certificate shall be submitted within one week.
The
matter to come up on 24.04.2023. |
ADJOURNMENT |
View Order |
| 20-Mar-2023 |
Sh. Shashank Sharma, Associate
Engineer Executive briefed about the facts of the project.
None is present on behalf of the
promoter.
The
matter to come up on 10.04.2023. |
EXAMINATION BY AUTHORITY |
View Order |