08-May-2023 |
Ar.
Neeraj Gautam, Associate Architectural Executive and Ms. Asha, Chartered
Accountant briefed about the facts of the case.
Sh.
Ashish Drall (Sr. GM) and Sh. Pankaj Sharma (Legal Manager) are present on the
behalf of the promoter.
The
promoter requests to grant registration subject to the submission of security
amount of Rs. 25 lacs in the Authority on account of submission of approved
service plans and estimates in the Authority within the stipulated time.
The Authority decides to grant registration subject to
the submission of DD/ Bank guarantee of Rs. 25 lacs in the Authority on account
of submission of approved service plans and estimates in the Authority within
three months from the date of grant of registration. The Authority shall be
free to forfeit this security amount in case the promoter fails to submit the
approval in the Authority within the stipulated time. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
01-May-2023 |
Due to administrative work, the matter is adjourned to 08.05.2023. |
ADJOURNMENT |
View Order |
17-Apr-2023 |
Ar. Neeraj Gautam, Associate Architectural Executive
and Ms. Asha, Chartered Accountant briefed about the facts of the case.
Sh. Ashish Drall (AR) and Sh. Pankaj Sharma (AR) are
present on the behalf of the promoter.
The AR of the promoter stated that they had submitted
the reply on 13.04.2023. The office to examine the same. The matter to come up
on 01.05.2023. |
ADJOURNMENT |
View Order |
29-Mar-2023 |
Ar. Neeraj Gautam, Associate Architectural Executive
and Ms. Asha, Chartered Accountant briefed about the facts of the case.
Sh. Ashish Drall and Sh. Pankaj Sharma are present on
the behalf of the promoter.
The AR of the promoter seeks two weeks time to comply
with the deficiencies.
The matter to come up on 17.04.2023. |
ADJOURNMENT |
View Order |
27-Mar-2023 |
The matter is adjourned to 29.03.2023. |
EXAMINATION BY AUTHORITY |
View Order |