Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
Paras Arcade 114 Sector - 114, Village Bajghera, Gurugram, Haryana GURUGRAM Harsaru ST Cordial Infrastructure Pvt. Ltd
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/708/440/2023/52 DATED 03.04.2023 RERA-GRG-1313-2023 02-Mar-2023 01-Mar-2023 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 16-Mar-2023 Online 1st deficiency notice
First hearing fixed View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/708/440/2023/52 DATED 03.04.2023 12-Jul-2023 RC Approved
Project Listing Details
Date of Hearing Proceedings of the day Status Order
03-Apr-2023 Sh. Sumeet, Engineer Executive and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Narender Singh (AR) and Sh. Aditya Shandilya (AR) are present on behalf of the promoter. The AR of the promoter states that the architectural control sheets have been approved from DTCP vide memo no. ZP-1751/JD(NK)/2023/9042 dated 29.03.2023 and the same are submitted in the authority on 31.03.2023. Further the AR states that they are submitting a cheque of Rs. 25 lakh as a security amount for submission of approved Service Plan and Estimates within three months of issuance of registration certificate. The AR further states that the approval of electrical, sewer, water and storm connection granted for earlier license may be considered as there is no increase in the load in the project. Further, the land title search report has already been examined at the level of DTCP while granting the license to the promoter and there is no such requirement. The AR of the promoter further assures that the balance documents will be corrected and submitted within two days. Keeping in view the above, the authority decides to grant the registration subject to the above compliances to be made by the promoter. APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
20-Mar-2023 Sh. Sumeet, Engineer Executive and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Narender Singh (AR) and Sh. Aditya Shandilya (AR) are present on behalf of the promoter. The reply to the deficiencies has been submitted today. Office to examine the same and put up before the next date of hearing. The matter to come up on 03.04.2023. EXAMINATION BY AUTHORITY View Order