| 03-Apr-2023 |
Sh.
Sumeet, Engineer Executive and Ms. Asha, Chartered Accountant briefed about the
facts of the project.
Sh.
Narender Singh (AR) and Sh. Aditya Shandilya (AR) are present on behalf of the
promoter.
The
AR of the promoter states that the architectural control sheets
have been approved from DTCP vide memo no. ZP-1751/JD(NK)/2023/9042 dated
29.03.2023 and the same are submitted in the authority on 31.03.2023. Further
the AR states that they are submitting a cheque of Rs. 25 lakh as a security
amount for submission of approved Service Plan and Estimates within three
months of issuance of registration certificate. The AR further states that the
approval of electrical, sewer, water and storm connection granted for earlier
license may be considered as there is no increase in the load in the project.
Further, the land title search report has already been examined at the level of
DTCP while granting the license to the promoter and there is no such
requirement. The AR of the promoter further assures that the balance documents
will be corrected and submitted within two days.
Keeping in view the above, the authority decides to
grant the registration subject to the above compliances to be made by the
promoter. |