04-Sep-2023 |
Ms. Prachi Singh Planning
Executive briefed about the facts of the
case.
Sh. Sanjeev Kumar (AR) is present on behalf of the
promoter.
The applicant states that the above project is for
development of 0.576 acres of commercial component as part of DDJAY plotted
colony which is already registered with the Authority under RC No.08 of 2022
dated 07.02.2022. Further, the service plans and estimates required to be
submitted in pursuance to the above registration has already been submitted in
the Authority on 01.09.2023 along with other deficit documents and that
development works have been completed and is applying to the DGTCP for grant of
CC. The promoter requests for grant of registration for above distinct
commercial project. Further, the promoter states
It is stated by the Project Executive that out of
three approvals required to be submitted by the promoter viz i) Zoning Plan ii)
Service Plans and Estimates and iii) GST Registration Certificate, Zoning Plan
and GST Registration Certificate have been submitted by the promoter on
13.04.2022 and 04.03.2022. It is further stated that vide reply dated
01.09.2023 the promoter has also submitted a copy of the approved service plans
and estimates which are yet to be examined. Further, it is noted that the
promoter has not filed QPR and 4(2)(l)(D) compliance in respect of the
registered project for which he seeks two weeks’ time.
After discussions, the Authority approved the grant of
registration for distinct commercial component subject to the submission of QPR
and 4(2)(l)(D) reports within a period of 2 weeks failing which penal
provisions as provided in the Act of 2016 are liable to be invoked. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
07-Aug-2023 |
Proceedings dated 07.08.2023
Ms. Prachi Singh Planning
Executive briefed about the facts of the
case.
Sh. Sanjeev Kumar (AR) is present on behalf of the
promoter.
The AR of the promoter requested for four weeks time
to submit compliances. Request is allowed.
The mater to come up on 04.09.2023. |
ADJOURNMENT |
View Order |
12-Jul-2023 |
Proceedings dated 29.05.2023
Ms. Prachi Singh Planning
Executive briefed about the facts of the
case.
Sh. Sanjeev Sharma, authorised representative is
present on the behalf of the promoter and states that the reply will be submitted today in the registry of the authority and seeks two weeks’ time.
Matter to come up on 12.6.2023 for further
proceedings. |
OBJECTION |
--- |
10-Jul-2023 |
Ms. Prachi Singh Planning
Executive briefed about the facts of the
case.
Sh. Sanjeev Sharma (AR) is present on the behalf of
the promoter and requests for three weeks’ time for compliance of deficiencies.
The promoter requested to amend the application for registration and apply for
commercial area only. The authority directs the applicant promoter that if the
promoter applicant wants, the application may be amended. The matter to come up
on 07.08.2023. |
ADJOURNMENT |
View Order |
12-Jun-2023 |
Ms. Prachi Singh Planning
Executive briefed about the facts of the
case.
Sh. Sanjeev Kumar (AR) is present on the behalf of the
promoter. The promoter is direct to remove the remaining deficiencies in the application
within one month. The separate proceedings for non- compliance of conditions of
RC should be initiated.
The matter to come up on 10.07.2023. |
ADJOURNMENT |
View Order |
29-May-2023 |
Proceedings dated 29.05.2023
Ms. Prachi Singh Planning
Executive briefed about the facts of the
case.
Sh. Sanjeev Sharma, authorised representative is
present on the behalf of the promoter and states that the reply will be submitted today in the registry of the authority and seeks two weeks’ time.
Matter to come up on 12.6.2023 for further
proceedings. |
EXAMINATION BY AUTHORITY |
View Order |