| 20-Mar-2023 |
Ms.
Prachi Singh, Planning Executive briefed about the facts of the case.
Sh.
Anurag Srivastava (Manager) is present on behalf of the promoter.
Approved
as proposed. |
EXTENSION APPROVED |
View Order |
| 06-Mar-2023 |
Ms.
Prachi Singh, Planning Executive briefed about the facts of the case.
Sh.
Anurag Srivastava (Manager) is present on behalf of the promoter.
The
AR of the promoter has submitted the reply to the deficiencies already
conveyed. The office to examine the same and to put up updated status before
the next date of hearing.
The
matter to come up on 20.03.2023. |
ADJOURNMENT |
View Order |
| 13-Feb-2023 |
Ms.
Prachi Singh, Planning Executive briefed about the facts of the case.
Sh.
Anurag Srivastava (AR) and Sh. Vedant (AR) are present on behalf of the promoter.
The
AR of the promoter seeks three weeks time. The request is allowed.
The
matter to come up on 06.03.2023. |
ADJOURNMENT |
View Order |
| 30-Jan-2023 |
The matter is adjourned to 13.02.2023. |
ADJOURNMENT |
View Order |
| 16-Jan-2023 |
The matter is adjourned to 30.01.2023. |
ADJOURNMENT |
View Order |
| 09-Jan-2023 |
The matter is adjourned to 16.01.2023. |
ADJOURNMENT |
View Order |
| 26-Dec-2022 |
The AR of the promoter is directed to remove the deficiencies and the matter is adjourned to 09.01.2023. |
EXAMINATION BY AUTHORITY |
View Order |