Project Name | Project Location | Project District | Project Tehsil | Promoter Name |
---|---|---|---|---|
Signature Global City 92-(II) | VILLAGE MEVKA, WAZIRPUR, SECTOR-92, GURUGRAM | GURUGRAM | Harsaru ST | Signature Infrabuild Pvt. Ltd. |
Project Registration Number | Project Id | Receiving Date | Online Submission Date | Current Status | Next Date of Hearing | Notice Dispatched | Notice Dispatched On | Notice Tracking Id | Notice Dispatched Remarks | View Notice | Initially Scrutinized Remarks | Details of Project(Form A-H) |
---|---|---|---|---|---|---|---|---|---|---|---|---|
GGM/666/398/2023/10 DATED 13.01.2023 | RERA-GRG-1220-2022 | 02-Dec-2022 | 02-Dec-2022 | APPROVED AND CERTIFICATE UPLOADED | NOT REQUIRED | Yes | 15-Dec-2022 | By Hand | Deficiency Notice | First hearing fixed | View Form(A-H) |
Project Registration Number | Uploading Date | Remarks | View Certificate |
---|---|---|---|
GGM/666/398/2023/10 DATED 13.01.2023 | 31-Jan-2023 | RC Uploaded |
Date of Hearing | Proceedings of the day | Status | Order |
---|---|---|---|
13-Jan-2023 | Approved as proposed. | APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS | View Order |
12-Jan-2023 | Sh. Anurag Srivastava (Manager) is present on behalf of the promoter. The promoter is advised to submit comparative statement of the changes in the lay out plan of the earlier registered part of the project along with tabulated form marking on the lay out plan. The matter to come up on 16.01.2023 if the information is supplied by tomorrow.The promoter has requested that matter may be fixed for tomorrow as the necessary information would be submitted tomorrow morning positively. Therefore, the matter is fixed for 13.01.2023. | ADJOURNMENT | View Order |
02-Jan-2023 | Ms. Prachi Singh, Planning Executive briefed about the facts of the case. Sh. Anurag Srivastava (Manager) is present on behalf of the promoter. The AR of the promoter is directed to clarify the position that whether DTCP has approved the revised layout plan of the colony area admeasuring 10.3 acres after incorporating the additional licensed area admeasuring 8.3125 acres with the prior written consent from two-third allottees of the earlier approved layout plan or not? Further, the promoter is directed to publish a public notice in two leading newspapers one Hindi and one English for inviting the objections from the existing allottees regarding the revision in the original layout plan and inspection of the above layout plans & application made by the promoter in the office of HARERA, Gurugram within 10 days. Further the promoter to submit comparative statement showing changes/variations made in the revised layout plan vis-a-viz earlier approved layout plan duly marked on copy of plan. The matter to come up on 12.01.2023. | ADJOURNMENT | View Order |
19-Dec-2022 | The AR of the promoter is directed to remove the deficiencies. The matter to come up on 02.01.2023 | EXAMINATION BY AUTHORITY | View Order |