| 19-Jun-2023 |
Ms.
Prachi Singh, Planning Executive briefed about the facts of the project.
Sh.
Parveen Kumar (AR), Sh. Virender Verma (AR) and Sh. Kamal Soni (AR) are present
on behalf of the promoter.
Approved
as proposed. |
EXTENSION APPROVED |
View Order |
| 29-May-2023 |
Ms. Prachi Singh, Planning Executive briefed about the facts of
the case is present on behalf of the promoter.
Sh. Parveen Kumar(AR) is present on behalf of the promoter.
Reply has been submitted by the promoter and seeks three weeks
time to rectify the deficiencies. Request is allowed. It is the last
opportunity to rectify the deficiencies.
Matter to come up on 19.6.2023 for further proceedings. |
ADJOURNMENT |
View Order |
| 15-May-2023 |
Ms.
Prachi Singh, Planning Executive briefed about the facts of the case.
Sh.
Parveen Kumar and Kamal Soni (AR) is present on behalf of the promoter. The
reply is submitted by the promoter which may be examined by the authority and
the matter to come up on 29.05.2023. |
OBJECTION |
View Order |
| 10-Apr-2023 |
Proceedings
dated: 10.04.2023
Ms.
Prachi Singh, Planning Executive briefed about the facts of the case.
The
promoter has neither appeared nor complied with the deficiency notices even
after multiple opportunities. A show cause notice for rejection of the
application for extension was also issued on 22.11.2022 and the situation
regarding the compliances remains unchanged. In view of the above, a
show cause notice under section 60 and 63 of the RERA Act, 2016 may be issued
to the promoter as to why a penalty amounting to 5% of the project cost may not
be imposed on the promoter.
The
matter to come up on 15.05.2023. |
ADJOURNMENT |
View Order |
| 20-Mar-2023 |
Ms.
Prachi Singh, Planning Executive briefed about the facts of the case.
Sh.
Kamal Kant Soni (AR) is present on behalf of the promoter. It has been
informed by the PE that QPRs and 4(2)(l)(D) compliances have not been submitted
by the applicant. The AR of the promoter states that the same shall be complied
with within a period of 15 days.
The
matter to come up on 10.04.2023. |
ADJOURNMENT |
View Order |
| 06-Mar-2023 |
Ms. Prachi Singh, Planning
Executive and Ms. Asha, Chartered Accountant briefed about the facts of the
case.
None is present on behalf of the promoter.
The matter is adjourned to 20.03.2023. |
ADJOURNMENT |
View Order |
| 14-Feb-2023 |
Ms.
Prachi Singh, Planning Executive briefed about the facts of the case.
Sh.
Kamal Soni (AR) is present on behalf of the promoter.
The
promoter is directed to rectify the deficiencies and submit the required
documents before the next date of hearing.
The
matter to come up on 06.03.2023. |
ADJOURNMENT |
View Order |
| 31-Jan-2023 |
The matter is adjourned to 14.02.2023. |
ADJOURNMENT |
View Order |
| 17-Jan-2023 |
The authorized representative of the promoter is advised to rectify the deficiencies and submit the deficit fee (if any) along with the deficit documents apart from the filing of information in online detailed project information. The matter is adjourned to 31.01.2023 |
ADJOURNMENT |
View Order |
| 03-Jan-2023 |
The authorized representative of the promoter is advised to rectify the deficiencies and submit the deficit fee (if any) along with the deficit documents apart from the filing of information in online detailed project information. The matter is adjourned to 17.01.2023 |
ADJOURNMENT |
View Order |
| 19-Dec-2022 |
The AR of the promoter is directed to remove the deficiencies. The matter to come up on 03.01.2023 |
ADJOURNMENT |
View Order |
| 15-Nov-2022 |
Proceedings dated 15.11.2022
Ms. Prachi Singh, Planning Executive briefed
about the facts of the project.
None is present on behalf of the promoter
despite service of the notice and conveying of the deficiencies notice which
includes non-payment of requisite fee, legal capacity as well as number of
other deficiencies conveyed.
A 30 days SCN be issued to the applicant as
to why the application be not rejected and the processing fee be forfeited.
The concerned Planning Executive to ensure issuance of the show cause notice
within next three days under signatures of Secretary, HARERA.
The matter to come up on 19.12.2022.
(Sanjeev Kumar Arora)
Member,
HARERA, Gurugram
(Ashok Sangwan)
Member,
HARERA, Gurugram
(Vijay Kumar Goyal)
Member,
HARERA, Gurugram
|
OBJECTION |
View Order |
| 18-Oct-2022 |
Proceedings
dated: 18.10.2022
Ms.
Prachi Singh, Planning Executive briefed about the facts of the project.
None
is present on behalf of the promoter.
Deficiencies have already been
communicated. Promoter is advised to rectify the deficiencies and submit
deficient documents, as detailed above.
Deficit fee, if any be also paid before the
next date of hearing along with proof of having deposited the deficit fee.
The promoter has requested for adjournment
for 15 days. Last opportunity is provided.
The
matter to come up on 15.11.2022. |
EXAMINATION BY AUTHORITY |
View Order |