21-Nov-2022 |
Ms. Deepika, Planning
Executive and Ms. Asha, Chartered Accountant briefed about the facts of the
project.
Sh. Dhiraj Goyal (AR) is
present on behalf of the promoter. The AR submits that the demarcation plan has
been checked and confirmed by STP Gurugram vide Memo No…. dated…..and sent to
DTCP for approval and issuance of zoning plan. As per Haryana Building Code,
2016, the zoning plan is required to be prepared and approved by DTCP on basis
of size and dimensions of the plots verified by STP in the demarcation plan and
the same is under approval/signatures of the DTCP. Further that the permissible
ground coverage, FAR, setbacks and height etc. are already fixed and provided
in the published Haryana Building Code and are to be incorporated in the zoning
plan accordingly and hence requests the Authority for issuance of registration
subject to submission of approved copy of zoning plan within 60 days. Similarly
the service plans and estimates have also been submitted and are under approval
of DTCP and requests for acceptance of cheque/BG subject to final submission of
approved copies of service plans estimates in 60 days. The Authority
considering the request of the AR allows grant of registration subject to the
condition that if the copy of approved zoning plan and approved service plans
and estimates are not submitted in 60 and 90 days respectively the cheque/BG
shall be forfeited. This is further subject to the conditions that till
submission of above approvals, there shall be no withdrawals from the RERA
account and the allottee shall have right to seek refund with interest if any
chooses to withdraw from the project on basis of zoning plan within 30 days of
their approval/uploading on the site.
Approved as proposed. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
16-Nov-2022 |
The matter is adjourned for 21.11.2022. |
ADJOURNMENT |
View Order |
14-Nov-2022 |
Ms. Deepika, Planning
Executive and Ms. Asha, Chartered Accountant briefed about the facts of the
project.
Sh. Dheeraj Goyal and Sh.
Sandeep Yadav are present on behalf of the promoter.
The
authority considered the application for registration of above-mentioned real
estate project u/s 4 of the Act of 2016. The promoter is required to enclose
the requisite documents as provided in section 4(2) of the Act of 2016 and the
rules and regulations made thereunder. The deficiencies have already been communicated
as detailed above.
The
matter to come up on 16.11.2022. (Sanjeev
Kumar Arora)
Member, HARERA, Gurugram
(Ashok
Sangwan)
Member, HARERA, Gurugram
(Vijay
Kumar Goyal)
Member, HARERA, Gurugram
(Dr. K.K. Khandelwal)
Chairman, HARERA, Gurugram
|
ADJOURNMENT |
View Order |
17-Oct-2022 |
Proceedings dated: 17.10.2022
Ms. Deepika, Planning
Executive and Ms. Asha, Chartered Accountant briefed about the facts of the
project.
Sh. Dhiraj Goyal (AS),
Sh. Charanjeet Monga (AS) and Sh. Sandeep Yadav (AR) are present on behalf of
the promoter.
Deficiencies
have already been communicated. Promoter is advised to rectify the
deficiencies and submit deficient documents, as detailed above. The promoter
is advised either to get the phasing approved from the DTCP or apply for the
whole licensed area.
The matter to come up on 14.11.2022
(Sanjeev
Kumar Arora)
Member, HARERA, Gurugram
(Ashok
Sangwan)
Member, HARERA, Gurugram
(Vijay
Kumar Goyal)
Member, HARERA, Gurugram
(Dr. K.K. Khandelwal)
Chairman, HARERA, Gurugram
|
EXAMINATION BY AUTHORITY |
View Order |