Comprehensive Project Details (Project Extension)
Project Location Details (Project Extension)
Project Name Project Location Project District Project Tehsil Promoter Name
Signature Global Park V VILLAGE HARIYAHARA, SECTOR-36 GURUGRAM SIGNATUREGLOBAL HOMES PRIVATE LIMITED
Project Detail
Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks
RERA-GRG-1163-2022 19-Sep-2022 19-Sep-2022 EXTENSION APPROVED NOT REQUIRED Not Yet -- First Hearing
Project Listing Details (Project Extension)
Date of Hearing Proceedings of the day Status Order
13-Mar-2023 Ms. Prachi Singh, Planning Executive briefed about the facts of the case.Sh. Anurag Srivastava (Manager) is present on behalf of the promoter.Approved as recommended.  EXTENSION APPROVED View Order
06-Mar-2023 Ms. Prachi Singh, Planning Executive briefed about the facts of the case. Sh. Anurag Srivastava (Manager) is present on behalf of the promoter. The AR of the promoter has submitted the reply to the deficiencies already conveyed. The office to examine the same and to put up updated status before the next date of hearing. The AR states that there are error in calculation of late fee calculated by the Authority and requests for its reconciliation. The CA and the concerned Planning Executive to jointly recheck and reconcile with AR of the promoter company.  The matter to come up on 13.03.2023.  ADJOURNMENT View Order
14-Feb-2023 Ms. Prachi Singh, Planning Executive briefed about the facts of the case. Sh. Anurag Srivastava (AR) is present on behalf of the promoter. The promoter is directed to rectify the deficiencies and submit the required documents before the next date of hearing. The matter to come up on 06.03.2023. ADJOURNMENT View Order
31-Jan-2023 The matter is adjourned to 14.02.2023. ADJOURNMENT View Order
17-Jan-2023 The authorized representative of the promoter is advised to rectify the deficiencies and submit the deficit fee (if any) along with the deficit documents apart from the filing of information in online detailed project information.  The matter is adjourned to 31.01.2023 ADJOURNMENT View Order
03-Jan-2023 The authorized representative of the promoter is advised to rectify the deficiencies and submit the deficit fee (if any) along with the deficit documents apart from the filing of information in online detailed project information.  The matter is adjourned to 17.01.2023 ADJOURNMENT View Order
19-Dec-2022 The AR of the promoter is directed to remove the deficiencies. The matter to come up on 03.01.2023 ADJOURNMENT View Order
05-Dec-2022 The authorized representative of the promoter is advised to rectify the deficiencies and submit the deficit fee within a week along with the deficit documents apart from the filing of information in REP-I A to H format and online detailed project information. Further, if any promoter has an issue regarding the calculation of the fee, then the same shall be re-conciled with the concerned official and be submitted in the Authority, otherwise their matter will not be heard on next date of hearing i.e., 19.12.2022. The matter to come up on 19.12.2022.                  (Sanjeev Kumar Arora) Member, HARERA, Gurugram (Ashok Sangwan) Member, HARERA, Gurugram (Vijay Kumar Goyal) Member, HARERA, Gurugram ADJOURNMENT View Order
15-Nov-2022 Proceedings dated 15.11.2022 Ms. Prachi Singh, Planning Executive briefed about the facts of the project. None is present on behalf of the promoter. The matter to come up on 05.12.2022.     (Sanjeev Kumar Arora) Member, HARERA, Gurugram (Ashok Sangwan) Member, HARERA, Gurugram (Vijay Kumar Goyal) Member, HARERA, Gurugram OBJECTION View Order
18-Oct-2022 Proceedings dated 18.10.2022 Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha (CA) briefed the facts of the case. Sh. Prabhjot Singh (Executive) is present on the behalf of the promoter. Deficiencies have already been communicated. Promoter is advised to rectify the deficiencies and submit deficient documents, as detailed above. Deficit fee, if any be also paid before the next date of hearing along with proof of having deposited the deficit fee. The matter to come up on 15.11.2022. OBJECTION View Order
28-Sep-2022  Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha (CA) briefed the facts of the case. Sh. Anurag Srivastava (GM) and Sh. Prabhjot Singh (Executive) is present on the behalf of the promoter. Deficiencies have already been communicated. Promoter is advised to rectify the deficiencies and submit deficient documents, as detailed above. Matter to come up on 18.10.2022. EXAMINATION BY AUTHORITY ---
Project Deficiency Details
Deficiency Date Deficiency Remarks Online Compliance Done Online Compliance Date Online Compliance Remarks Compliance Date Compliance Remarks
21-Oct-2022 Proceedings dated 18.10.2022 Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha (CA) briefed the facts of the case. Sh. Prabhjot Singh (Executive) is present on the behalf of the promoter. Deficiencies have already been communicated. Promoter is advised to rectify the deficiencies and submit deficient documents, as detailed above. Deficit fee, if any be also paid before the next date of hearing along with proof of having deposited the deficit fee. The matter to come up on 15.11.2022. Not Yet
30-Sep-2022  Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha (CA) briefed the facts of the case. Sh. Anurag Srivastava (GM) and Sh. Prabhjot Singh (Executive) is present on the behalf of the promoter. Deficiencies have already been communicated. Promoter is advised to rectify the deficiencies and submit deficient documents, as detailed above. Matter to come up on 18.10.2022. Not Yet