02-Feb-2023 |
Sh. Sumeet, Engineer Executive and
Ms. Asha Chartered Accountant briefed about the facts of the case.
Sh. Dheeraj Yadav, Sh. Amit Yadav
(Director) and Sh. Dheeraj Sood are present on behalf of the promoter.
The applicant/ promoter has
obtained BIP permission approved in-principle by DTCP subject to compliance of
conditions and the AR submits that the requisite compliances has been submitted
in DTCP office. Further, the AR seeks
three months time for submission of the approved service plan and estimates and
fire NOC for which two no. of cheques have been submitted.
The proposal for
grant of registration is approved subject to submission of final BIP permission.
Further a penalty of Rs 50 lakhs is imposed under section 59(1) for violation
of section 3 of RERA, 2016 for which a show cause notice vide no.
RERA-GRG-4829-2022 dated 14.07.2022 stands issued and to be deposited before
issuance of registration certificate. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
31-Jan-2023 |
The matter is adjourned to 02.02.2023. |
ADJOURNMENT |
View Order |
30-Jan-2023 |
The matter is adjourned to 31.01.2023. |
ADJOURNMENT |
View Order |
23-Jan-2023 |
The matter is adjourned to 30.01.2023. |
ADJOURNMENT |
View Order |
02-Jan-2023 |
Sh. Sumeet, Engineer Executive and
Ms. Asha Chartered Accountant briefed about the facts of the case.
Sh. Amit Yadav (Director) and Sh.
Dheeraj Sood (AR) are present on behalf of the promoter.
The ARs of the promoter are directed to
remove the deficiencies and submit the deficit documents as detailed above.
The matter is
adjourned to 23.01.2023. |
ADJOURNMENT |
View Order |
19-Dec-2022 |
The AR of the promoter is directed to remove the deficiencies. The matter to come up on 02.01.2023 |
ADJOURNMENT |
View Order |
12-Dec-2022 |
The matter is adjourned to 19.12.2022 |
ADJOURNMENT |
View Order |
28-Nov-2022 |
The
authorized representative of the promoter is advised to rectify the
deficiencies and submit the deficit fee (if any) along with the deficit documents
apart from filing information in REP-I A to H format and online detailed
project information. Matter to come up
on 12.12.2022 |
ADJOURNMENT |
View Order |
14-Nov-2022 |
Sh. Sumeet, Engineer
Executive and Ms. Asha Chartered Accountant briefed about the facts of the
case.
None is present on
behalf of the promoter.
The authority
considered the application for registration of above mentioned real estate
project u/s 4 of the Act of 2016. The promoter is required to enclose the
requisite documents as provided in section 4(2) of the Act of 2016 and the
rules and regulations made thereunder. The deficiencies have already been
communicated as detailed above.
The promoter is
advised to rectify the deficiencies within 15 days otherwise the Authority may
proceed to initiate proceedings to reject the application u/s 5(1)(b) of Act of
2016 read with rule 5 of the Haryana Rules, 2017 for the reason regarding
deficiencies in the application and non-submission of requisite documents.
The promoter is
already facing penal proceedings under section 59 of the Act of 2016 for the
violation of section 3 of the Act of 2016. These proceedings will also be
clubbed with this application and matter be heard jointly.
The matter to come
up on 28.11.2022. |
ADJOURNMENT |
View Order |
31-Oct-2022 |
The matter is adjourned to 14.11.2022 |
EXAMINATION BY AUTHORITY |
View Order |